Question
A contractor hired 50 workers to complete a work in 80
days. After 50 days, it was found that only 1/4th of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.Solution
ATQ, Total work = 50workers × 80days = 4000worker-days Work completed = 1/4 of total work = 4000/4 = 1000 worker-days Remaining work = 4000 worker-days − 1000 worker-days = 3000 worker-days Days left =80 days − 50 days = 30 days Hence, Number of workers needed = {3000 worker-days/30 days} =100 workers Therefore Number of extra workers required: Extra workers needed = 100 workers − 50 workers = 50 workers Thus, the contractor needs to hire 50 extra workers to complete the work on time.
Which of the following statements regarding an auditor's responsibilities is FALSE?
Which form is required for preparing the Revenue account in insurance company engaged in general insurance business?
Within how many days an employee can apply for gratuity from the date when gratuity becomes payable?
Shyam Ltd. acquired a new machinery for ₹ 1,00,000 that is depreciable at 20% as per AS 6 WDV method. The machine has an expected life of 5 years with...
What does ETF stand for in Bharat Bond ETF?
As per section 408 of the Companies Act the National Company Law Tribunal shall consist of ________________
Section 115JAA allows which of the following?
The process of finding present value of a future amount is called:
X Ltd. is committed to supply 24,000 bearings per annum to Y Ltd. on steady basis. It is estimated that it costs 10 paise as inventory holding cost per ...
Sovereign Gold Bonds (SGBs) are issued in India by: