Question
A contractor hired 50 workers to complete a work in 80
days. After 50 days, it was found that only 1/4th of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.Solution
ATQ, Total work = 50workers × 80days = 4000worker-days Work completed = 1/4 of total work = 4000/4 = 1000 worker-days Remaining work = 4000 worker-days − 1000 worker-days = 3000 worker-days Days left =80 days − 50 days = 30 days Hence, Number of workers needed = {3000 worker-days/30 days} =100 workers Therefore Number of extra workers required: Extra workers needed = 100 workers − 50 workers = 50 workers Thus, the contractor needs to hire 50 extra workers to complete the work on time.
What type of radiation is produced by a hot object emitting energy? Â
A plane mirror is placed on a wall. A man walks directly toward the mirror at 2 m/s. The speed at which his image approaches him is:
If a force of 20 N is applied to push a 4 kg object, what is the acceleration produced? Â
What does 'IC' stand for in electronics?
Which of the following is a reason for excessive current in electrical circuits?
I. Direct touching of wires
II. Connection of many d...
Which of the following is the SI unit of electric charge?
Why does a lemon appear larger when viewed from the side of a glass of water?
If a body of mass 5 kg is raised to 10 meters height, find its potential energy. (g = 9.8 m/s²) Â
Planck’s constant has dimensions equivalent to which of the following?
Which quantity has the same dimensional formula as impulse?