Question
A contractor hired 50 workers to complete a work in 80 days. After 50 days, it was found that only 1/4th of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.
More Time and work Questions
- Three workers A, B and C can complete a job in 12, 15 and 20 days respectively, working alone. All three start working together. After some time, C leaves,...
- A can complete 5/6 of a work in 15 days and B can complete 2/3 of work in 8 days. In how many days both A and B together can complete the work?
- P and Q agreed to complete a task for Rs. 6600. P can finish the work alone in 12 days, and Q can complete it alone in 10 days. If they work together, what...
- 'P' and 'Q' together can complete the work in 12 days. 'Q' alone can complete the work in 20 days. If R is 25% more efficient than P, find the time taken b...
- A alone can finish a piece of work in 10 days and B alone can finish it in 15 days. They work together for 3 days and the remaining work is finished by C i...
- ‘A’ and ‘B’ can do a piece of work in 20 days and 40 days, respectively. If they started the work together and worked on it for 6 days, then find the time ...
- A can complete a piece of work in 20 days, and B in 30 days. They work together for 6 days, after which A leaves. In how many more days will B finish the r...
- Three workers, A, B, and C, can complete a task in 40 days, 72 days, and 45 days respectively. They start working together, but A leaves 20 days before the...
- A alone can complete 60% of a work in 36 days while B takes 30 days more than A to complete it. If B and C together can complete the work in 40 days, then ...
- ‘A’ can do a piece of work in 12 days. ‘B’ can do 60% of the same work in 18 days. If they work together for the entire time and get paid Rs.1540, then fin...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt