Question
A contractor hired 50 workers to complete a work in 80
days. After 50 days, it was found that only 1/4th of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.Solution
ATQ, Total work = 50workers × 80days = 4000worker-days Work completed = 1/4 of total work = 4000/4 = 1000 worker-days Remaining work = 4000 worker-days − 1000 worker-days = 3000 worker-days Days left =80 days − 50 days = 30 days Hence, Number of workers needed = {3000 worker-days/30 days} =100 workers Therefore Number of extra workers required: Extra workers needed = 100 workers − 50 workers = 50 workers Thus, the contractor needs to hire 50 extra workers to complete the work on time.
Which of the following integrity constraints ensures that every non-null foreign key value must reference an existing primary key value in another tabl...
Hashing is used for:
The amortized cost of appending an element at the end of a dynamic array is:
Consider the following stack operations. What will be the content of the stack after executing all the operations?
Stackstack = new Stack... Which of the following is NOT among the OWASP Top 10 Web Security Risks?
In Python, what will be the output of the following code snippet, considering scope rules?
x = 5
In asymmetric encryption, which of the following statements is correct?
Which algorithm constructs a suffix tree in linear time?
What is the primary purpose of a B+ Tree in a database management system?
Which sorting algorithm has O(n log n) average case?