Question
A contractor hired 50 workers to complete a work in 80
days. After 50 days, it was found that only 1/4th of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.Solution
ATQ, Total work = 50workers × 80days = 4000worker-days Work completed = 1/4 of total work = 4000/4 = 1000 worker-days Remaining work = 4000 worker-days − 1000 worker-days = 3000 worker-days Days left =80 days − 50 days = 30 days Hence, Number of workers needed = {3000 worker-days/30 days} =100 workers Therefore Number of extra workers required: Extra workers needed = 100 workers − 50 workers = 50 workers Thus, the contractor needs to hire 50 extra workers to complete the work on time.
- If Rina can complete a project in 36 days by working 9 hours a day, how many hours per day should she work to complete the project in 18 days?
A and B together can do a work in 10 days. A alone can do it in 15 days. In how many days can B alone do it?
P works thrice as fast as Q, whereas P and Q together can work four times as fast as R. If P&Q and R together work on a job, in what ratio should they s...
Vijay can do a piece of work in 32 days and Sanjay can do the same work in 48 days. If Vijay works for 2 days and got Rs. 960, and the remaining work wi...
‘A’ alone can complete a work in 20 hours. ‘A’ started the work alone and left after working on it for 15 hours. If ‘B’ completed the rest o...
A can fabricate a divider in 23 days , while B alone can assemble it in 26 days, If they construct it together and get an installment of Rs 9800, then f...
The total present ages of 'X', 'Y' and 'Z' is 150 years and the average of present ages of 'X' and 'Z' is 44 years. 5 years ago, 'Y' was twice as old as...
Working 10 hours a day, Jagan can complete a work in 12 days while working 8 hours a day, Magan can complete the same work in 9 days. If Jagan and Magan...
Ratio of the work done by P, Q and R in one day is 7:3:8 respectively. They all together can complete the work in 42 days. Q and R worked on it for 21 d...
Asmita and Bhanu working together can complete the task in ____ days, and the efficiency of Sam is 50% more than that of Asmita. Bhanu alone can complet...