Question

A contractor hired 50 workers to complete a work in 80 days. After 50 days, it was found that only 1/4th of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.

A 10
B 25
C 50
D 65
E None of these
Practice Next

More Time and work Questions

Hey! Ask a query