Question
A contractor hired 50 workers to complete a work in 80
days. After 50 days, it was found that only 1/4th of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.Solution
ATQ, Total work = 50workers × 80days = 4000worker-days Work completed = 1/4 of total work = 4000/4 = 1000 worker-days Remaining work = 4000 worker-days − 1000 worker-days = 3000 worker-days Days left =80 days − 50 days = 30 days Hence, Number of workers needed = {3000 worker-days/30 days} =100 workers Therefore Number of extra workers required: Extra workers needed = 100 workers − 50 workers = 50 workers Thus, the contractor needs to hire 50 extra workers to complete the work on time.
In India, field experiments on water management falls in____________ approach
For Magnesium deficiency determination, plant that is used as indicator plant _________________________ .
Which of the following soil types has the highest water-holding capacity but is prone to poor aeration and slow permeability?
Which test is used to evaluate seedling vigor under stress conditions?
According to the law of demand, what is the relationship between price and quantity demanded
Scientific name of soybean is:
Which disease induces floral abnormalities like phyllody?
Which of following fungi is not used as a bio-control agent of plant diseases?
The rate of decrease of temperature with height is known as:
Which of the following refers to process element of the marketing mix?