Question
A contractor hired 50 workers to complete a work in 80
days. After 50 days, it was found that only 1/4th of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.Solution
ATQ, Total work = 50workers × 80days = 4000worker-days Work completed = 1/4 of total work = 4000/4 = 1000 worker-days Remaining work = 4000 worker-days − 1000 worker-days = 3000 worker-days Days left =80 days − 50 days = 30 days Hence, Number of workers needed = {3000 worker-days/30 days} =100 workers Therefore Number of extra workers required: Extra workers needed = 100 workers − 50 workers = 50 workers Thus, the contractor needs to hire 50 extra workers to complete the work on time.
Which of the following numbers does not fit into the pattern of the series?
8, 27, 64, 100, 125, 216, 343
Which number will replace the question mark (?) in the following number series?
 5, 4, 6, 15, 56, ?
A @ B means ‘A is the husband of B’
A & B means ‘A is the mother of B’
A # B means ‘A is the daughter of B’
If Q ...
With reference to the PM CARES Fund, consider the following statements:
I. The amount collected by it directly goes to the Consolidated Fund of I...
Select the correct mirror image of the given figure when the mirror MN is placed to the right side of the figure.
Select the option that is related to the fifth word in the same way as the fourth word is related to the third word and the second word is related to th...
Select the figure from the options that when placed in the blank space of the given figure will complete the pattern.
Statements:
All holders are hangers.
All hangers are hammers.
Some hammers are axes.
Conclusions:
I. Some axes ar...
Statement:
A. All germanium is lithium.
B. Some deuteron are plumbum.
C. Some germanium is chlorine.
Conclusion:
(I) ...
There are some nectar filled flowers on a tree and some bees are hovering on it. If one bee lands on each flower, one bee will be left out. If two bees ...