Question
A contractor hired 50 workers to complete a work in 80
days. After 50 days, it was found that only 1/4th of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.Solution
ATQ, Total work = 50workers × 80days = 4000worker-days Work completed = 1/4 of total work = 4000/4 = 1000 worker-days Remaining work = 4000 worker-days − 1000 worker-days = 3000 worker-days Days left =80 days − 50 days = 30 days Hence, Number of workers needed = {3000 worker-days/30 days} =100 workers Therefore Number of extra workers required: Extra workers needed = 100 workers − 50 workers = 50 workers Thus, the contractor needs to hire 50 extra workers to complete the work on time.
If tan A = 1 and tan B = √ 3, what is the value of cos A . cos B - sin A . sin B?
If (sin 3A sec 6A = 1) , then what will be the value of cos 6A?
If secθ + tanθ = 3+√10, then the value of sinθ+cosθ is
If tan A =
, find the va...
The minimum value of 9 cos2 θ + 36 sec2 θ isÂ
Find the value of the following:sin(36° + A) × cos(54° – A) + cos(36° + A) × sin(54°–A)
- If 2 sin x = √3, then the value of x:
If tan θ = 8/3 , then the value of (3Sinθ+2 Cosθ )/(3 Sinθ-2Cosθ) is
From a point "A" on the ground, the angle of elevation to the top of a tower measuring 12 meters in height is 30°. Determine the horizontal distance be...