Question
A contractor hired 50 workers to complete a work in 80
days. After 50 days, it was found that only 1/4th of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.Solution
ATQ, Total work = 50workers × 80days = 4000worker-days Work completed = 1/4 of total work = 4000/4 = 1000 worker-days Remaining work = 4000 worker-days − 1000 worker-days = 3000 worker-days Days left =80 days − 50 days = 30 days Hence, Number of workers needed = {3000 worker-days/30 days} =100 workers Therefore Number of extra workers required: Extra workers needed = 100 workers − 50 workers = 50 workers Thus, the contractor needs to hire 50 extra workers to complete the work on time.
600 Â Â Â 60Â Â Â 12Â Â Â ? Â Â Â Â 1.44Â Â Â Â 0.72
42, 48, 60, 84, 132, ?
78, 88, 100, 114, ?, 148
4097, ?, 4359, 4493, 4629, 4767
13, 28, ?, 118, 238, 478
51 26 27 ? 86 217.5
15.5, 62, 186, ?, 2232, 8928
17, 36, 65, 104, 153, ?
6848 + 9215 – 7295 - ? = 5945 – 3244
What will come in place of the question mark (?) in the following series?
7, 19, 55, 163, 487, ?