Question
A can finish a task by himself in 25 days, whereas B can
finish the same task by himself in 10 days. A begins the task but stops after 5 days, at which point B takes over and finishes the job. How many total days were required to complete the task?Solution
Let the total work = 50 units (L.C.M of 25 and 10) Efficiency of A = 50/25 = 2 units/day Efficiency of B = 50/10 = 5 units/day Amount of work done by A in 5 days = 2 × 5 = 10 units Remaining work = 50 – 10 = 40 units Time taken by B to complete the remaining work = 40/5 = 8 days Total number of days = 8 + 5 = 13 days
Which of the following is/are the machinery for the settlement of Industrial disputes?
I. Labour Court
II. ...
Two dice are thrown simultaneously. The probability that the product of the two numbers on the two dice is an even number is
The LCM of 84, 105 and 140 is:
The provisions related to retrenchment are covered under which Act?
A credit purchase of machinery recorded in the Purchase Book instead of Journal Proper is an example of:
Fruits stored in a cold chamber exhibit longer storage life because
Which one of the following is not a correct description of the Namami Gange Programme ?
Which of the following molecular interactions is the strongest in stabilizing the tertiary structure of proteins?
Which one of the following has the characteristics of both an animal as well as a plant?
The money multiplier in an economy increases with which one of the following?