Question
A can finish a task by himself in 25 days, whereas B can
finish the same task by himself in 10 days. A begins the task but stops after 5 days, at which point B takes over and finishes the job. How many total days were required to complete the task?Solution
Let the total work = 50 units (L.C.M of 25 and 10) Efficiency of A = 50/25 = 2 units/day Efficiency of B = 50/10 = 5 units/day Amount of work done by A in 5 days = 2 × 5 = 10 units Remaining work = 50 – 10 = 40 units Time taken by B to complete the remaining work = 40/5 = 8 days Total number of days = 8 + 5 = 13 days
In which year of amendment, the list of Unfair Labour Practices was adopted in Industrial Dispute Act 1947?
According to a report by prominent online blogging platform soic.in,which state in India has emerged as the largest economy with the highest GDP share i...
What describes a situation where the rate of inflation is slowing down?
Under the provisions of the Industrial Disputes Act 1947, the employer of any industry declares lay-off, is required to provide alternate employment to ...
Which of the following statements is/ are correct?
1. Budget Division of Department of Economic affairs prepares the budget
2. ...
Which of the following option is incorrect about “PM Swasthya Suraksha Yojana”?
Which one of the following is a natural substitute for common sugar?
Which Author has been selected for Saraswati Samman 2022?
The ratio of total additional planned savings in an economy to the total additional income of the economy is known as:
Match the following correctly;