📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    âš¡ Month End Offer - Flat 52% Off On All Courses! Enroll Now âš¡
    00:00:00 AM Left

    Question

    P alone can finish a piece of work ‘M’ in 6

    days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work ‘N’ which is 6 times of work ‘M’ in 6 days. How long will R take to finish work ‘N’, when working alone?
    A 16 days Correct Answer Incorrect Answer
    B 15 days Correct Answer Incorrect Answer
    C 13.5 days Correct Answer Incorrect Answer
    D 12 days Correct Answer Incorrect Answer
    E 14 days Correct Answer Incorrect Answer

    Solution

    Let the work ‘M’ = 6 units (LCM of 6 and 3) Efficiency of P = 6/6 = 1 units Efficiency of Q = 6/3 = 2 units Efficiency of P, Q and R = (6 × 6)/6 = 6 units per day Efficiency of R = 6 – (1 + 2) = 3 units per day Time taken by R to finish work ‘N’ = 36/3 = 12 days

    Practice Next
    ask-question