Question
Ashish and Anil can do a piece of work in 20 days and 25
days respectively. Ashish completed 60% of the work. Find the time taken by Anil to complete the remaining work.Solution
Let the total work be (LCM of 20 and 25) = 100 units Efficiency of Anil = 100/25 = 4 units/day Remaining work = 100 x 0.4 = 40 units Time taken by Anil to complete the remaining work = 40/4 = 10 days
State Bank of India (SBI), has floated a green rupee term-deposit scheme to raise money for financing environment-friendly projects. Which of the follow...
Prime Minister Shri Narendra Modi government’s Pradhan Mantri Jan Dhan Yojana has completed how many years in India?
World Athletics has awarded the 'Woman of the Year' accolade to ____________.
Consider the following statements -
I. YES Bank has received a green signal from the Reserve Bank to make I-Process Services (India) Private Ltd ...
What is the full form of βFINOβ, a term we see frequently in financial newspapers?
The Persian film Endless Borders directed by Abbas Amini received the Golden Peacock award for the Best Film at the 54th IFFI. What is the Prize Money f...
What is the total YoY percentage increase in National Pension System ( NPS ) assets, including Atal Pension Yojana, from December 9 of the previous year...
Which of the followings Indian company is the biggest private airport operator in India?
Collarwali tigress, also known as T-15, passed away in _____ Tiger Reserve in Madhya Pradesh.
REC inks how many strategic MoUs in backdrop of Madhya Pradesh Global Investors Summit 2023?