Question
Shudhanshu completes 1/2 of work in 12 days, then he
completes the remaining work with the help of Neeraj in 5 days. The time required for Sudhanshu and Neeraj together to complete the entire work isÂSolution
If Sudhanshu alone can do half of a job in 12 days So, remaining part is done by Sudhanshu & Neeraj both in 5 days So, they will complete the entire work in =Â 5/(1/2) = 10 days.
Name of Albania’s AI Cabinet Minister avatar?
Which of the following substance produces brisk effervescence when treated with baking-soda solution?
Algae often float on surface of water during day but sink during night due to:Â Â
Which organ controls reflex actions?
Kindly Study the following questions carefully and choose the right answer.
Which of the following is/are true with respect to Amoeba?
I...
The main function of centriole is:
Silicon is an example ofÂ
Which of the two temperature scales are same ?
 The site where complete digestion of carbohydrates, proteins and fats takes place is called
Which one of the following gases is supporter of combustion?