A red JCB machine can complete the excavation of a field
in 10 days, while a green JCB machine can accomplish the same task in 15 days. If both machines operate simultaneously for 4 days, what fraction of the field will they have excavated together?Solution
Let total work = 150 units Amount of work done by Red JCB machine in one day = 150/10 = 15 units Amount of work done by Green JCB machine in one day = 150/15 = 10 units Amount of work done by both machine in one day = 15 + 10 = 25 units Time taken by both machines together to complete the work = 150/25 = 6 days So the part of work done by both the machines together in 4 days = 4/6 = 2/3 Hence, option d.
Browsing the
P- bibliophile’s fantasy
Q- towering columns
R- of books is a
Which of the following words would fit in the blank given in Statement D?
The question below consists of a set of labelled sentences. These sentences, when properly sequenced form a coherent paragraph. Select the most logical ...
- Parts of a sentence are given below in jumbled order. Arrange the parts in the correct order to form a meaningful sentence.
P. and reusing material... Select the option that arranges sentences A, B, C and D in a logical sequence.
A. This reputation overwhelms his record and when people think of ...
1. There was no proper light system on the highway
P.In addition, clouds were gathering in the sky.
Q.The night was darker than usual.
...Improve the bold part of the sentence.
He explained the rules clearly so as everyone could understand them easily.
In each of the questions given below a sentence is given with three words in bold. Choose the option which gives the correct sequence of these words to ...
Which should be the last sentence after rearrangement?
Which of the following is the sixth (last) sentence of the passage?