Question
A red JCB machine can complete the excavation of a field
in 10 days, while a green JCB machine can accomplish the same task in 15 days. If both machines operate simultaneously for 4 days, what fraction of the field will they have excavated together?Solution
Let total work = 150 units Amount of work done by Red JCB machine in one day = 150/10 = 15 units Amount of work done by Green JCB machine in one day = 150/15 = 10 units Amount of work done by both machine in one day = 15 + 10 = 25 units Time taken by both machines together to complete the work = 150/25 = 6 days So the part of work done by both the machines together in 4 days = 4/6 = 2/3 Hence, option d.
When a metal reacts with dilute hydrochloric acid, it produces:
Which of the following element is required for the conversion of the solar energy?Â
A battery of emf 12 V and internal resistance 4 ohm is connected to a resistor. If the current in the circuit is 0.6 A, what is the resistance of the re...
Which blood group is the universal recipient?
Deficiency of which vitamin leads to bleeding gums?
Natural radioactivity was discovered byÂ
What is the reason for twinkling of stars?
What is the most basic criteria used to decide whether something is alive?
The SI unit of mechanical power is:Â
The SI unit of surface tension is: