Question
A red JCB machine can complete the excavation of a field
in 10 days, while a green JCB machine can accomplish the same task in 15 days. If both machines operate simultaneously for 4 days, what fraction of the field will they have excavated together?Solution
Let total work = 150 units Amount of work done by Red JCB machine in one day = 150/10 = 15 units Amount of work done by Green JCB machine in one day = 150/15 = 10 units Amount of work done by both machine in one day = 15 + 10 = 25 units Time taken by both machines together to complete the work = 150/25 = 6 days So the part of work done by both the machines together in 4 days = 4/6 = 2/3 Hence, option d.
With reference to the Global Financial Innovation Network (GFIN), consider the following statements:
I.        It is a consortium of o...
What is the main objective of the Pradhan Mantri Jan Dhan Yojana?
Who among the following said, "Employee welfare means anything done for the comfort and improvement, intellectual or social, of the employees over and a...
Which Indian city was recently ranked the 12th richest city globally?
Which of the following statements is/are incorrect about the “Wholesale Price Index (WPI)”?
I.        WPI does not capture changes...
Which of the following are the key actors in industrial relations according to Dunlop's System Theory?Â
Which of the following is not included in the National Income?
Match the following correctly;
What type of economy does India have?
"ILO Conference No. 87" sometimes seen in the news is related to which of the following?