Question
Sudhanshu completes `1/3` of work in 12 days,
then he completes the remaining work with the help of Neeraj in 4 days. The time required for Neeraj alone to complete the entire work isSolution
Sudhanshu can do 1/3rd work in 12 days So he can do total work in 36 days. They both can do remaining work (2/3) in 4 days So they can do total work in 6 days. Sudhanshu Sudhanshu+Neeraj 36 6 36 1 : 6 So neeraj 1 day work = 6 - 1 = 5 units So he can do total work in = 36/5 days
What is the position of P with respect to her sister?
Eight friends, Q, R, S, T, U, V, W and X are sitting in a line facing north. U is sitting at one of the corners. R is sitting between X and S. W is sitt...
Six girls, P, Q, R, S, T and V, are sitting around a circular table. All of them are facing towards the centre of the table (but not necessarily in the ...
Six people, F, G, H, I, J and K are sitting around a circular table facing towards the centre (but not necessarily in the same manner). One person is s...
How many people live between the floors on which Tanya and the one eating Sandwich live?
Which of the following statements is/are not true regarding I?
Who among the following lives on the floor immediately above the floor of G?
How many candidates sit in the row?
T, C, P, N and S are five friends sitting in a row facing south. S is sitting exactly between C and N. P is not the immediate neighbour of C and T does ...
Who among the following is an immediate neighbor of Pallav and Padma?