Question
Sudhanshu completes `1/3` of work in 12 days,
then he completes the remaining work with the help of Neeraj in 4 days. The time required for Neeraj alone to complete the entire work isSolution
Sudhanshu can do 1/3rd work in 12 days So he can do total work in 36 days. They both can do remaining work (2/3) in 4 days So they can do total work in 6 days. Sudhanshu Sudhanshu+Neeraj 36 6 36 1 : 6 So neeraj 1 day work = 6 - 1 = 5 units So he can do total work in = 36/5 days
Which of the following is an example of two-factor authentication?
What is a key characteristic of dynamic programming?
In a B+ tree, the leaf nodes are typically connected in a linked list to facilitate:
Which of the following is NOT a common type of firewall?
Physical limitation of a signal is called?
What is the purpose of the "GROUP BY" clause in an SQL query?
Storage capacity of magnetic disk depends on
In which type of scope do variables declared in a function have priority over variables declared in the surrounding program?
Which SQL keyword is used to remove rows from a table?
A control unit in a CPU uses a microprogram to: