Question
βPβ alone can paint a house in 18 days, while
βPβ and βQβ together can do it in 12 days. If βQβ started the work and left after 6 days, how many days will βPβ take to complete the painting?Solution
ATQ,
Let the total work = 36 {L.C.M of 18 and 12}
Efficiency of βPβ = 36 Γ· 18 = 2 units/day
Combined efficiency of βPβ and βQβ = 36 Γ· 12 = 3 units/day
So, efficiency of βQβ alone = 3 β 2 = 1 unit/day
Work done by βQβ in 6 days = 1 Γ 6 = 6 units
Remaining work = 36 β 6 = 30 units
Time taken by βPβ alone = 30 Γ· 2 = 15 days
More Time and work Questions
- A series is given with one term missing. Choose the correct alternatives from the given ones that will complete the series.
57, 59, 56, 61, 54, ___ - Which letter-cluster will replace the question mark (?) in the following series?
RGV, UME, ?, AYW, DEF - Which letter and number cluster will replace the question mark (?) to complete the given series?
LT6, KU12, IW24, FZ48, ____ - Which letter-cluster will replace the question mark (?) in the following series?
NPQR, OORQ, PNSP, ____, RLUN - Select the number from among the given options that can replace the question mark (?) in the following series.
17, 18, 22, 31, 47, ___