Question
βPβ alone can paint a house in 18 days, while
βPβ and βQβ together can do it in 12 days. If βQβ started the work and left after 6 days, how many days will βPβ take to complete the painting?Solution
ATQ,
Let the total work = 36 {L.C.M of 18 and 12}
Efficiency of βPβ = 36 Γ· 18 = 2 units/day
Combined efficiency of βPβ and βQβ = 36 Γ· 12 = 3 units/day
So, efficiency of βQβ alone = 3 β 2 = 1 unit/day
Work done by βQβ in 6 days = 1 Γ 6 = 6 units
Remaining work = 36 β 6 = 30 units
Time taken by βPβ alone = 30 Γ· 2 = 15 days
What is βNon-Interest Incomeβ of banks?
Consider the following statement with reference to the Special Drawing Rights(SDRs).
A) It is an international reserve asset created by the IM...
Which of the following is the secondary function of Banks?
I. Collecting and supplying business information.
II. Issuing letters of c...
The inability of aΒ debtor Β to pay theirΒ debt is known as..........................
What is the full form of MDR ?
Who has been elected president of the Paralympic Committee of India?
Arrange the Following banks in ascending order in their respective establishment years.
(A) Corporation BankΒ Β Β Β (B) Punjab National BankοΏ½...
Which of the following is true about role of Banks?
I. It facilitates import export transactions.
II. It helps in national developmen...
What is the term used for the practice of replacing relatively high cost debt with that of lower cost borrowing to take advantage of falling interest ra...
Which one of the following statements is true