Question

‘P’ alone can paint a house in 18 days, while ‘P’ and ‘Q’ together can do it in 12 days. If ‘Q’ started the work and left after 6 days, how many days will ‘P’ take to complete the painting?

A 20 days
B 18 days
C 12 days
D 15 days
E None of these