Question
P and Q can complete a work in 20 days and 30 days,
respectively. P, Q and R together can complete the work in 10 days. If R get a total wage of Rs. 4800 to complete the work alone, then find the per day wage of R.Solution
Let the total work be LCM of (20, 30 and 10) = 60 units Number of units of work done by P alone in one day = 60/20 = 3 units Number of units of work done by Q alone in one day = 60/30 = 2 units Number of units of work done by P, Q and R together in one day = 60/10 = 6 units Number of units of work done by R alone in one day = 6 – 3 – 2 = 1 unit So, time taken by R alone to complete the work = 60/1 = 60 days So, per day wage of R = 4800/60 = Rs. 80
The unit of communication at the data link layer is a .......................,,,,,,,,,,,,,
Which of the following best describes cloud computing?
What is the range of IP addresses for Class B networks?
How to verify that while sending confidential information over the Internet such as usernames, passwords, or credit card numbers, sent data is encrypted
Which network protocol is responsible for assigning IP addresses to devices dynamically in a network?
Which of the following is the primary function of a router?
An example of a telecommunications device is a ________.
The “home page” of a web site is _________.
What is the purpose of a Honeypot in network security?
Which of the following hardware can provide Firewall security