Question
P and Q can complete a work in 20 days and 30 days, respectively. P, Q and R together can complete the work in 10 days. If R get a total wage of Rs. 4800 to complete the work alone, then find the per day wage of R.
More Time and work Questions
- C is 37.5% more efficient than A, and A is 60% more efficient than B. If A, B, and C together can complete a task in 40 days, how long will it take A alone...
- A, B, and C can finish work in 5 days, 10 days, and 15 days, respectively, working alone. A and B work on the first day, A and C work on the second day, A ...
- 'X' and 'Y' can complete a certain job together in 36 days. They worked together for 20 days, after which 'X' left, and 'Y' completed the remaining work al...
- What is B’s share (in ₹)? I: A and B together can complete a piece of work in 12 days. B and C together can complete the same work in 16 days. A and C tog...
- 55 men can complete a piece of work in 12 days. 15 men started the same work and worked for 10 days, and then joined by ‘x’ more men such that the remainin...
- A is twice as efficient as B. Together they can complete a work in 18 days. In how many days can A alone complete the work?
- A alone can complete a piece of work in 15 days, while B alone can complete it in 20 days. They start the work together, and after some days A leaves. B co...
- 40 men can complete a piece of work in 48 days. ‘x’ men started the work and after 30 days 56 more men joined them so that whole work was finished in the d...
- Two candles of same height can burn completely in 8 hours and 12 hours respectively. If both start burning at same time at their respective constant speed,...
- A and B together can complete a work in 15 days, while B and C together can complete the same work in 20 days. If A, B, and C together can complete the wor...