Question
‘R’ completes a job in 10 days. ‘S’ is twice as efficient as ‘R’. How much time will they take to complete 120% of the work together?
Solution
Let total work = 100x units.
Efficiency of R = 100x / 10 = 10x units/day.
S is twice as efficient, so S's efficiency = 2 × 10x = 20x units/day.
120% of work = 100x × 1.20 = 120x units.
Combined efficiency = 10x + 20x = 30x units/day.
Time taken = 120x / 30x = 4 days.
More Time and work Questions
- Two pipes, P and Q, can fill a tank in 60 minutes and 100 minutes, respectively. A third pipe R can empty it in 1 hour 40 minutes. Initially, pipes P and R...
- A’ and ‘B’ alone can do a certain work in 20 days and 30 days, respectively. Both started the work together but after ‘x’ days ‘A’ left the work and the re...
- A work can be completed by ‘A’ and ‘B’, alone in 15 days and 20 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if...
- (x + 8) men working 9 hours a day can complete 60% of a work in 12 days. (x + 2) men working 3 hours a day can complete the remaining work in 32 days. Find...
- A can finish a piece of work in 10 days and B can finish it in 15 days. If both work together, in how many days will the work be completed?
- A and B working together, can do a piece of work in 4(1/2) hours. B and C working together can do it in 3 hours. C and A working together can do it in 2(1/...
- 50 workers working 6 hours a day take 18 days to complete a task. How many workers working for 5 hours a day are needed to complete four times the given ta...
- R and S take 10 days and 15 days respectively to complete a task alone. If they alternate work every day starting with R, how much time will it take to fin...
- A alone can complete a work in 16 days and B alone in 12 days. Starting with A, they work on alternate days. In how many days, total work will be completed...
- 'N,' 'V,' and 'R' have individual work completion times of 140 days, 112 days, and 80 days, respectively. They all started working together on a task, but ...