Question
P and Q together can complete 75% of a work in 15 days
while Q alone takes 40% more time than P and Q together to complete the whole work. Find the time taken by P alone to complete 90% of the work.Solution
ATQ, Time taken by P and Q together to complete the whole work = 15/0.75 = 20 days Time taken by Q alone to complete the whole work = 1.40 × 20 = 28 days Total work = 140 units (LCM of 20 and 28) Amount of work done by P and Q together in one day = 140/20 = 7 units Amount of work done by Q alone in one day = 140/28 = 5 units Amount of work done by P alone in one day = 7 – 5 = 2 units Desired time = (0.90 × 140)/2 = 63 days
'Browning of cauliflower disease is attributed to the plant deficiency of the micronutrient
‘Kresek’ symptom is a characteristic symptom of which disease of rice?Â
The air temperature drop with increasing altitude. The average decrease in temperature drop is approximately _______. This is also known as “Environme...
Japanese style of floral arrangement is termed as
Phosphorus availability to plants is the maximum in the pH range of:
Which agro climatic region has highest intensity of agriculture in the country?
Dihybrid ratio 9:3:3:1 in F2 results due to independent assortment of :
President of ICAR is
Eye drops are example of
Application developed by Indian institute of wheat and barley research for pest management in wheat crop is