Question
Aarif, Arun, and Abraham can do work in 12, 15, and 24
days, respectively. They all begin together. Aarif leaves the work 1 day, Arun 3 days and Abraham 4 days before its completion. In how many days is the work finished?Solution
Aarif Arun Abraham 12 15 24 120 10 8 5 Let, they do not leave and do some extra work. Extra Work=10×1+8×3+5×4=54 Total work =120+54=174units Time taken =174/23days. =7(13/23)days
What is the main goal of machine learning in AI?
Which of the following is an example of an ADT for storing data?
Which command is used to copy a file from one location to another in a Unix/Linux system?
Which layer of the OSI model provides services for file transfer, email, and network management?
What is the first phase in the software development process?
A control unit in a CPU uses a microprogram to:
The Traveling Salesperson Problem is an example of which complexity class?
Which device is responsible for making routing decisions in a network?
COCOMO is based on which type of estimation approach?
The ALU (Arithmetic Logic Unit) is responsible for: