Question
If one man or two women or four boys or five girls can
finish a work in 39 days, then how many days will one man, one woman, one boy and one girl together take to finish the same work.Solution
1M =2W=4B=5G=39 Men,WomenBoysGirls 3978156195 780-LCM 201054-Efficiency Work of (M+W+B+G) =780/39=20days
How many 5-digit numbers can be formed using digits 1 to 5 without repetition such that the number is divisible by 5?
'P' sold an item at a profit of 40%. If the cost price of the item had been Rs. 150 less and its selling price had been Rs. 30 mo...
30.22% of (61.9 × 5.01) + 59.97 =?Â
if p:q = 3:4 and q:r = 1:2, the find the value of (4p + 3q + r):(2p + 5q - r)
A trader bought two articles for ₹2,000 and ₹3,000. He sold the first article at a profit of 20% and the second article at a loss of 10%. What is th...
What is the remainder when 26×28×32 is divided by 25?
The average age of three friends Maya, Nirmal, and Raju is 27 years. The age ratio of Nirmal to Raju is 9:5, and Maya is 11 years...
In a 1500-metre race, Arjun beats Bishnu by 600 metres, and Bishnu beats Chintu by 700 metres. How far will Arjun beat Chintu by ...
Find the area enclosed between the curves y=(x−4)2 and y=16−x2over their intersection interval.
Which component of a computer is responsible for managing and coordinating various hardware components?