Question
55 men can complete a piece of work in 18 days. ‘x’ men started the work and after 9 days 64 more men joined them so that whole work was finished in the desired time. Find the value of ‘x’
More Time and work Questions
- A can finish a piece of work in 10 days and B can finish the same work in 15 days. If they work together, in how many days will the work be completed?
- Virat can do a piece of work in 26 days and Sachin can do the same work in 39 days. If Virat works for 5 days and got Rs. 3000, and the remaining work will...
- 'Pooja' can complete a work in 28 days. She started the work and left after 14 days from starting. The remaining work was done by 'Ritika' in 21 days. Find...
- Consider that 'A' and 'B' were collectively paid Rs. 9,000 for a job. Out of this amount, 'B' received Rs. 3,000. If 'B' can finish this task solo in 48 da...
- 15 men can complete a piece of work in 5 days, while 20 women can complete it in 5 days. 8 men start working on the job & after working for 3 days, all of ...
- Pipes X and Y can fill a tank in 48 minutes and 80 minutes respectively. Another pipe Z can empty the tank in 2 hours. X and Z are opened together. If afte...
- Person 'X' can finish a task in 40 days while 'Y' can do it in 50 days. How long will it take if both work together?
- A and B can complete a task together in 26 days, while B alone takes 52 days to finish it. A began working alone and left after ‘x’ days, after which B com...
- Anu can finish 25% of an assignment in 10 days, whereas Tanya can do 30% in 12 days. Anu works on it for 16 days and leaves. How long will Tanya take to wr...
- The team of A B and C was supposed to complete a piece of work. Working alone, A could have completed the same work in 190 hours. B could have completed th...