Question

"A" can complete a task in 15 days, while it takes 25 days for "B" to complete the same task. The ratio of the efficiencies of "A" and "C" is 2:1. If a task takes 30 days for 2A, 3B, and 4C working together, find out the number of tasks that were achieved.

A 50
B 15.05
C 25.12
D 11.6
E none of these