Question
Ratio of the work done by P, Q and R in one day is 7:3:8
respectively. They all together can complete the work in 42 days. Q and R worked on it for 21 days. In how many days P will complete the remaining work.Solution
Let total amount work be = 42 x 18 = 756 units Amount of work done by Q and R in 21 days = 21 x 11 = 231 units Amount of work left = 756 – 231 = 525 Required time = 525/7 = 75 days
According to the Reserve Bank of India (Transfer to Public Ownership) Act, 1948, which led to the nationalization of the Reserve Bank of India, what ha...
In which of the following does the river Godavari originate?
Where in India, the World’s largest wildlife rescue centre, “Vantara”, has been inaugurated?
 Consider the following statements in reference to the Phylogenetic classification system.
1.   It shows an evolutionary relationship ...
What does SIDBI stand for?
In which state, Kudankulam Nuclear Power Plant is established?Â
Which of the following policies is aimed at reducing the fiscal deficit in India?
When did the Union Cabinet approved the setting up of National Recruitment Agency to conduct the Common Eligibility Test?
Pin Valley National Park is situated in which state?
The Ministry of Women and Child Development (MoWCD) is an apex body for formulation and administration of the rules and regulations and laws relating to...