Question
Ratio of the work done by P, Q and R in one day is 7:3:8
respectively. They all together can complete the work in 42 days. Q and R worked on it for 21 days. In how many days P will complete the remaining work.Solution
Let total amount work be = 42 x 18 = 756 units Amount of work done by Q and R in 21 days = 21 x 11 = 231 units Amount of work left = 756 – 231 = 525 Required time = 525/7 = 75 days
How many transactions did UPI process in December 2024?
What is the length of the Nimmu-Padam-Darcha road?Â
The Union Minister of State (Independent Charge) for Science & Technology unveiled a new variety of lotus named 'NBRI Namoh 108,' developed by CSIR-NBRI...
What major regulatory change did SEBI propose to make rights issues more attractive?
Where are the headquarters of Indian Bank ?
Which of the following public sector oil company had launched HaPpy Shop store for costumers in affordable prize for home utility products including foo...
In December 2021, IIT-_______ signed an MoU with the Indian Air Force (IAF) for various developmental projects to support the requirements of the IAF.
Pope Francis, who passed away in 2025, had led the Catholic Church since which year?
Which country has India allowed to export an additional 251 MW of electricity recently?
Which country will host the 2027 FIFA Women’s World Cup for the first time in Latin America?