Question
A man, a woman, a boy, and a girl can complete a certain task individually in 84 days, 105 days, 140 days, and 210 days respectively. How long will it take for all four of them working together to complete the task?
Solution
Let the total work = L.C.M of 84, 105, 140, and 210 = 420 units
Efficiency of a man = 420 Γ· 84 = 5 units/day
Efficiency of a woman = 420 Γ· 105 = 4 units/day
Efficiency of a boy = 420 Γ· 140 = 3 units/day
Efficiency of a girl = 420 Γ· 210 = 2 units/day
So, time taken by a man, a woman, a boy and a girl working together = 420 Γ· (5 + 4 + 3 + 2) = 30 days
More Time and work Questions
- Karan, Arjun and Krunal alone can complete a work in 40, 60 and 48 days respectively. All of them started working together but after 3 days from start Kara...
- Rajesh and Bhupesh can complete a piece of work in 20 days and Bhupesh alone in 25 days. In how many days can Rajesh alone complete the work?
- A worker completes 30% of a job in 6 days. Assuming the same rate of work, in how many total days will he complete the whole job?
- In an office, an employee plans to do a work in 20 days with 6 laptops. But after 10 days, he found that only 40% of the work is done with the laptops work...
- 35 men can complete a piece of work in 40 days. βxβ men started the work and after 30 days 60 more men joined them so that whole work was finished in the d...
- A can complete a piece of work in 24 days. He worked for 21 days and then B finished the remaining work in 6 days. In how many days can A and B finish the ...
- Arjun and Karan can do a work separately in 20 days and 50 days respectively. Arjun started the work and was later joined by Karan. When should Karan join ...
- Working alone, B can complete the work in 30 days. C is twice as efficient as B and A takes 20 days more than it takes C to complete the work. Working toge...
- 50% of the work done by Meena in 2 days is equal to 25% of the work done by Lata in 5 days. If Meena can complete the job alone in 10 days, then how long w...
- Ten men begin to do work. But after some days, four of them left the job. As a result, the job that could have been completed in 40 days is completed in 50...