Question
A man, a woman, a boy, and a girl can complete a certain task individually in 84 days, 105 days, 140 days, and 210 days respectively. How long will it take for all four of them working together to complete the task?
More Time and work Questions
- A and B can complete a task in 6 days working together. A alone works twice as fast as B. If A works alone for 2 days and B finishes the rest, how many mor...
- A takes twice as much time as B and thrice as much time as C to finalize a task. Working together, they can complete the task in 8 days. The time (in days)...
- ‘C’ is 20% less productive compared to ‘B’, who is 25% more productive than ‘A’. Together, they finish a job in 40 days. After ‘A’ and ‘B’ have worked for ...
- Akhil and Nikhil together can complete a work in 5 days while Nikhil alone takes 10 days to complete 40% of the work. If the efficiency of Sachin is 25% mo...
- Nikhil and Rohit together can complete a job in 105 days 8 minutes, while Rohit and Suresh together can finish the same job in 70 days 5 minutes. If Suresh...
- Alok and Vinay can complete some work alone in 12 days and 20 days respectively. Both of them started the work together but Vinay left the work 4 days befo...
- P, Q, and R can complete a work in 12 days. 15 days and 30 days, respectively, working alone. How soon can the work be completed if Q is assisted by P and ...
- 'A', 'B' and 'C', alone can do some work in 15 days, 18 days and 30 days, respectively. If they work together for wages of Rs. 9,800, then find the differe...
- R and S take 10 days and 15 days respectively to complete a task alone. If they alternate work every day starting with R, how much time will it take to fin...
- 12 man can make a wall in 5 days. How many men required to complete the same work in 6 days ?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt