Question
If 18 men working 18 hours a day can make 18 quilts in
18 days, then in how many days 27 men working 12 hours per day will make 27 quilts?Solution
Let the number of days be x. According to question, => (18 ×  18 ×  18)/18 = (x × 12 × 27)/27 => x = 27
Who is the founder of “Jainism”?
How much money did HUDCO raise in its maiden foray into the syndicated loan market?
Since when has the newspaper 'Garhwali' been published in Dehradun?
Which nationwide campaign has been launched in honour of the martyred brave soldiers of the country?
With reference to the Zoji La Pass, consider the following statements:
1.   It is a high mountain pass located in the Kargil district of Lada...
Which organization recently completed six consecutive developmental trials of the High-Speed Expendable Aerial Target (HEAT) 'ABHYAS'?
Which entity has Adani International Ports Holdings Pvt. Ltd (AIPH) signed the concession agreement with to operate Container Terminal 2?
Consider the following statements about Propane:
1. Recently, SAIL has inked a 15-year agreement BPCL to supply propane
2. It is produ...
 India's first booster vaccine, GEMCOVAC-OM, is designed to target which COVID-19 variant?
Who has been awarded the Nobel Peace Prize for the year 2023?