Question

If 18 men working 18 hours a day can make 18 quilts in 18 days, then in how many days 27 men working 12 hours per day will make 27 quilts?

A 18 Correct Answer Incorrect Answer
B 27 Correct Answer Incorrect Answer
C 10 Correct Answer Incorrect Answer
D 16 Correct Answer Incorrect Answer

Solution

Let the number of days be x. According to question, => (18 ×  18 ×  18)/18 = (x × 12 × 27)/27 => x = 27