A painter charges ₹500 for every hour of work. If he works for 6 hours a day and completes a project in 5 days, what is the total amount charged by the painter for the project?
More Time and work Questions
- 16 men or 24 women can complete a piece of work in 36 days. A man and a woman together complete the work and receive a total wage of Rs. 9,600. Find the di...
- R and S take 10 days and 15 days respectively to complete a task alone. If they alternate work every day starting with R, how much time will it take to fin...
- The ratio of time taken by P, Q and R to complete work alone is 6:8:4 respectively. If all three together complete the work in 8 days, then find in how man...
- Armaan and Bhanu working together can finish a certain task in 90 days, and Bhanu collaborating with Chintu can complete the same task in 70 days. If Armaa...
- In a retreat, there is sufficient food for 300 people for the duration of the retreat. After 8 days, 100 people leave the retreat. Then, after another 3 da...
- ‘A’ and ‘B’ can do a piece of work in 30 days and 20 days, respectively. If they started the work together and worked on it for 4 days, then find the time ...
- Armaan can complete a task in 36 days, Bittu in 45 days, and Chirag in 60 days. If Bittu and Chirag together work on the task for 10 days, how many additio...
- A and B finish a job together in 36 days, while B and C together finish it in 48 days. The trio completes 75% of the job in 18 days. In how many days will ...
- Mira is 40% more efficient than Priya, and Neha is 10% more efficient than Mira. If Neha and Mira together can do a piece of work in 15 days, in how many d...
- A alone can assemble 40 mobile phones in 10 hours, while B alone can assemble the same number in 15 hours. Working together, in how many hours can A and B ...