Question
A and B can together complete a work in 8 days, B and C in 12 days, and C and A in 16 days. In how many days can C alone complete the work?
Solution
ATQ, Let daily work rates of A, B, C be a, b, c. a + b = 1/8 b + c = 1/12 c + a = 1/16 Add all: 2(a + b + c) = 1/8 + 1/12 + 1/16 LCM(8,12,16) = 48 1/8 = 6/48, 1/12 = 4/48, 1/16 = 3/48 Sum = 13/48 β a + b + c = 13/96 Now: a = (a + b + c) β (b + c) = 13/96 β 1/12 1/12 = 8/96 β a = (13 β 8)/96 = 5/96 β A alone: 96/5 = 19.2 days b = (a + b + c) β (c + a) = 13/96 β 1/16 1/16 = 6/96 β b = (13 β 6)/96 = 7/96 β B alone: 96/7 days c = (a + b + c) β (a + b) = 13/96 β 1/8 1/8 = 12/96 β c = (13 β 12)/96 = 1/96 β C alone: 96 days. Hence, C alone can complete work in 96 days
- Karan, Arjun and Krunal alone can complete a work in 40, 60 and 48 days respectively. All of them started working together but after 3 days from start Kara...
- Rajesh and Bhupesh can complete a piece of work in 20 days and Bhupesh alone in 25 days. In how many days can Rajesh alone complete the work?
- A worker completes 30% of a job in 6 days. Assuming the same rate of work, in how many total days will he complete the whole job?
- In an office, an employee plans to do a work in 20 days with 6 laptops. But after 10 days, he found that only 40% of the work is done with the laptops work...
- 35 men can complete a piece of work in 40 days. βxβ men started the work and after 30 days 60 more men joined them so that whole work was finished in the d...
- A can complete a piece of work in 24 days. He worked for 21 days and then B finished the remaining work in 6 days. In how many days can A and B finish the ...
- Arjun and Karan can do a work separately in 20 days and 50 days respectively. Arjun started the work and was later joined by Karan. When should Karan join ...
- Working alone, B can complete the work in 30 days. C is twice as efficient as B and A takes 20 days more than it takes C to complete the work. Working toge...
- 50% of the work done by Meena in 2 days is equal to 25% of the work done by Lata in 5 days. If Meena can complete the job alone in 10 days, then how long w...
- Ten men begin to do work. But after some days, four of them left the job. As a result, the job that could have been completed in 40 days is completed in 50...