Question
‘X’ and ‘Y’ together can complete a work in 10 days, while ‘Y’ and ‘Z’ together can complete the work in 8 days. If ‘Y’ takes 12 days to complete the work alone then find the approximate time taken by all three together to complete 65% of work.
More Time and work Questions
- ‘A’ alone can complete a piece of work in 30 days while ‘A’ and ‘B’ together can complete the same work in 20 days. ‘B’ started the work and after 4 days ‘...
- A work can be completed by ‘A’ and ‘B’, alone in 7 days and 14 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if ...
- A is twice as efficient as B. Together they can complete a work in 18 days. In how many days can A alone complete the work?
- A does 2/5 of a work in 9 days. Then B joined him and they together completed the remaining work in 6 days. B alone can finish the whole work in
- Three boys can do a work in 15 days where as 6 girls can do in 12days. What will be the time taken to complete the same work by a teacher if the efficiency...
- Working 10 hours a day, Jagan can complete a work in 12 days while working 8 hours a day, Magan can complete the same work in 9 days. If Jagan and Magan wo...
- P can construct a robot individually in 20 hours, while Q requires 40 hours to complete the same task. If they collaborate, how many hours will it take the...
- A and B together can do a piece of work in (p-8.8) days.The efficiency of D is 10% less than the efficiency of B. A and C together can do the same piece of...
- A is thrice as efficient as B and can finish a piece of work in 28 days less than B. B can finish this work in how many days?
- Three workers A, B and C can complete a job in 12, 15 and 20 days respectively, working alone. All three start working together. After some time, C leaves,...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt