      Question

      β€˜X’ and β€˜Y’ together can complete a work in 10

      days, while β€˜Y’ and β€˜Z’ together can complete the work in 8 days. If β€˜Y’ takes 12 days to complete the work alone then find the approximate time taken by all three together to complete 65% of work.
      A 33 days Correct Answer Incorrect Answer
      B 47 days Correct Answer Incorrect Answer
      C 29 days Correct Answer Incorrect Answer
      D 5 days Correct Answer Incorrect Answer
      E 16 days Correct Answer Incorrect Answer

      Solution

      Let the total work = 120 units Efficiency of (X + Y) = 120/10 = 12 units/day Efficiency of (Y + Z) = 120/8 = 15 units/day Efficiency of β€˜Y’ = 120/12 = 10 units/day Efficiency of (X + Y + Z) = (12 + 15 – 10) = 17 units/day Required time taken = (0.65 Γ— 120)/17 = 5 days (approx)