Question
βAβ and βBβ can complete a certain work in 12
days and 24 days, respectively. They started working together and worked till completion of the work for which they got Rs. 24000 as wage. Find the share of βBβ out of total wage.Solution
Let total work = 24 units {LCM of (12 and 24)} Efficiency of βAβ = 24/12 = 2 units/day Efficiency of βBβ = 24/24 = 1 units/day Wages received by βAβ and βBβ will directly proportion to their efficiency. So share of βBβ = 24000 Γ (1/3) = Rs 8000
Which of the following is a basic equation used in the COCOMO model?
How many stable states does a positive-edge-triggered D-type flip-flop have?
Basic syntax to create a bar-chart in R is
Which of the following is a component of a combined cycle power plant?
Which are types of system design
Which SQL keyword is used to remove rows from a table?
Which is the correct format specifier for double type value in C?
Which concurrency control technique allows a transaction to read uncommitted data?
keyword is used to skip this iteration and move to next iteration ?
Which type of digital circuit produces an output solely based on its current inputs and doesn't have any memory elements?