Question

'Pooja' can complete a work in 28 days. She started the work and left after 14 days from starting. The remaining work was done by 'Ritika' in 21 days. Find the time taken by 'Ritika' to complete 50% of the work.

A 25 days
B 17 days
C 21 days
D 63 days