Question
'Pooja' can complete a work in 28 days. She started the
work and left after 14 days from starting. The remaining work was done by 'Ritika' in 21 days. Find the time taken by 'Ritika' to complete 50% of the work.Solution
ATQ,
Fraction of work completed by 'Pooja' = (14/28) = (1/2)
Remaining work = 1 - (1/2) = (1/2)
Time taken by 'Ritika' to complete (1/2)th of the work = 21 days
Time taken by 'Ritika' to complete the whole work = 21 × (2/1) = 42 days
Therefore, time taken by 'Ritika' to complete 50% of the work = 0.5 × 42 = 21 days
Where will the first-ever Street 20 World Cup cricket tournament for street children be held?
India's garment exports have faced challenges in recent years. According to a research report, which of the following is identified as the primary reaso...
According to SEBI’s proposed rules for Real Estate Investment Trusts (REITs), what financial instrument can REITs use to hedge against interest rate f...
Which Padma Shri awardee participated in the Sewa Parv 2025 workshops at Maheshwar?
What is the maximum collective investment cap for Regulated Entities (REs) in any Alternative Investment Fund (AIF) scheme, effective from January 1, 2026?
The first India Stack Developer Conference held in ____?
What amount has the Asian Development Bank (ADB) approved for a policy-based loan to improve India's health system?
PM SHRI Yojana, which was recently implemented in Delhi, is associated with which field?
Which statements correctly describe the NIRMAN portal launched by Union Minister Shri G Kishan Reddy?
1. The portal is for Civil Services Examina...
Who inaugurated the national seminar on 'Tribes of Keonjhar: People, Culture and Heritage' and an exhibition of tribal costumes, jewelry, and food items...