Question
'Ramesh' can complete a work in 40 days. He started the
work and left after 24 days from starting. The remaining work was done by 'Suresh' in 30 days. Find the time taken by 'Suresh' to complete 75% of the work.Solution
ATQ,
Fraction of work completed by 'Ramesh' = (24/40) = (3/5)
Remaining work = 1 - (3/5) = (2/5)
Time taken by 'Suresh' to complete (2/5)th of the work = 30 days
Time taken by 'Suresh' to complete the whole work = 30 Ă (5/2) = 75 days
Therefore, time taken by 'Suresh' to complete 75% of the work = 0.75 Ă 75 = 56.25 days
Which of the following is not a money market instrument?
âSwachh Bharat Missionâ is associated with which public figure?
Who among the following had been appointed as the Director-General of National Security Guard (NSG) by the Appointments Committee of the Cabinet led by...
The Chinese traveller Huien Tsang visited India during which kingâs rule?
In which year was the first Economic Census carried out in India?
In which year Wahida Rahman was honored with the Padma Bhushan Award, one of India's civilian awards?
Under Pradhan Mantri Kisan Maandhan Yojana the farmers would receive a minimum assured pension of Rs ____ per month after attaining the age of 60 years ...
âSaid (Syad) Jagarâ reflects to:
Indian men's hockey team won the bronze medal by defeating which country in Tokyo 2020 Summer Olympics in August 2021?
Enhanced Access & Service Excellence (EASE) was launched in January 2018 and the GoI has launched the 5th version of EASE i.e. EASE 5.0, which is not a ...