Question

'Ramesh' can complete a work in 40 days. He started the work and left after 24 days from starting. The remaining work was done by 'Suresh' in 30 days. Find the time taken by 'Suresh' to complete 75% of the work.

A 25 days
B 17.5 days
C 21.6 days
D 56.25 days
Practice Next

More Time and work Questions

Hey! Ask a query

🎓
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
  • 200 Questions with Detailed Solutions
  • Section-wise Coverage (GA, English, Quant & Reasoning)