Question
'Ramesh' can complete a work in 40 days. He started the
work and left after 24 days from starting. The remaining work was done by 'Suresh' in 30 days. Find the time taken by 'Suresh' to complete 75% of the work.Solution
ATQ,
Fraction of work completed by 'Ramesh' = (24/40) = (3/5)
Remaining work = 1 - (3/5) = (2/5)
Time taken by 'Suresh' to complete (2/5)th of the work = 30 days
Time taken by 'Suresh' to complete the whole work = 30 × (5/2) = 75 days
Therefore, time taken by 'Suresh' to complete 75% of the work = 0.75 × 75 = 56.25 days
At what age did Gael Monfils become the oldest player to win an ATP Tour title?
Which campaign, recently launched, focuses on showcasing recent success stories in various scientific fields?
Consider the following statements about State Food Safety Index:
1. Recently, Ministry of Commerce published the State Food Safety Index.
...
What is India’s rank in the Henley Passport Index 2024?
Within what timeframe does the startup policy of Uttarakhand aim to achieve the promotion of 1000 startups?
Which of the following does not belong to Manipuri Women's Traditional Clothing?
Prime Minister Shri Narendra Modi launched how many PARAM Supercomputers in India?
Who became the 1st Indian to win the first-ever medal at the Asian fencing championships held in Wuxi, China?
Which Hollywood actor and producer will be honored with the prestigious Satyajit Ray Lifetime Achievement Award at the 54th International Film Festival ...
When do we celebrate National Consumer Rights Day annually?