Question
Rahul, Sameer, and Dinesh can
complete a task in 24 days, 36 days, and 18 days, respectively. They started working together, but Rahul left after 3 days. How long will it take Sameer and Dinesh to finish the remaining task?Solution
ATQ,
Let the total work be 432 units. Efficiency of Rahul = 432 ÷ 24 = 18 units/day Efficiency of Sameer = 432 ÷ 36 = 12 units/day Efficiency of Dinesh = 432 ÷ 18 = 24 units/day Work done in the first 3 days = 3 × (18 + 12 + 24) = 162 units Remaining work = 432 – 162 = 270 units Required time = 270 ÷ (12 + 24) = 270 ÷ 36 = (135/13) or Â
What is full form of LiFE at the side event held at India Pavilion at COP 27?
The Clean Plant Programme (CPP) under the Mission for Integrated Development of Horticulture emphasizes inclusivity. Which group is explicitly mentioned...
Concerning Western disturbances, consider the following statements:
1. These are weak tropical cyclones that originate over the Mediterranean ...
The Global Rank of India in fish production in 2022 is …………………….
Agricultural Census is conducted by Ministry Of Agriculture every ______years with the participation of states and UTs since 1970 as a part of World Agr...
India is the second Largest Producer of Rice Globally with a record rice production in 2021-22 is about ……………………..
...Recently Union Minister Shri Piyush Goyal announced for the integration of ODOP initiative with Open Network for Digital Commerce (ONDC), what is the fu...
India’s first greenfield grain based ethanol production plant inaugurated in ………………….
The birth anniversary of Vergese Kurien is remarked as National Milk day and is celebrated on
Which of the following country approved the commercial cultivation of GM Mustard?