πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      A builder employed 12 workers to complete a job in 18 days.

      But after 8 days, 4 workers quit. How many more days will be required to complete the remaining work?
      A 5 days Correct Answer Incorrect Answer
      B 4 days Correct Answer Incorrect Answer
      C 3 days Correct Answer Incorrect Answer
      D 7 days Correct Answer Incorrect Answer

      Solution

      ATQ,

      Let the efficiency of each worker be 'e' units/day.

      So, total work = 12 Γ— 18 Γ— e = 216e units

      And work done in first 8 days = 12 Γ— 8 Γ— e = 96e units

      So, work left = 216e - 96e = 120e units

      Now, remaining workers = 12 - 4 = 8

      So, time needed = 120e Γ· (8 Γ— e) = 15 days

      Additional days = 15 - 10 = 5 days

      Practice Next

      Relevant for Exams:

      ask-question