Question
A contractor assigned 18 laborers to complete a task in 16
days. Unfortunately, 6 laborers left after 6 days. How many additional days will be required to finish the work?Solution
ATQ,
Let each laborer's efficiency be 'e' units/day
Total work = 18 × 16 × e = 288e units
Work done in 6 days = 18 × 6 × e = 108e units
Remaining work = 288e - 108e = 180e units
Laborers left = 18 - 6 = 12
Time required = 180e ÷ (12 × e) = 15 days
Extra days = 15 - 10 = 5 days
Answer the questions based on the information given below.
A & B means A is greater than B
A * B means A is not greater than B
A ...
Statements: M % N, N & A, A @ B, B # C
Conclusions: I. C & AÂ Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â II. M # B
...Statements: R > S > T ≥ U; Q ≥ R; W = V < U
Conclusions:
I. S > Q
II. W < T
III. Q > W
In the following question the relationship between different elements is given in the statements followed by three conclusions I, II and III. Read the...
In the question, assuming the given statements to be true, find which of the conclusion (s) among given three conclusions is /are definitely true and ...
Statements:
N < P ≤ I = O; P ≥ J ≥ K ≥ W; Z ≤ M ≤ W
Conclusions:
I) O > Z
II) O = Z
...Statements: M $ K; K & N, N % R, R @ W
Conclusions:Â Â Â Â Â
I. W & KÂ Â Â Â Â Â Â Â
II. K & WÂ Â Â Â Â Â Â Â Â Â Â Â ...
Statements: I ≥ E = S > J < N > V > Q ≤ O
Conclusion
I: I > S
II: Q < N
In the question, assuming the given statements to be true, find which of the conclusion (s) among given two conclusions is /are definitely true and the...
Statements: F > V > W ≥ L > G; F ≤ O = M < I
Conclusions: I. M > LÂ Â Â II. V < I