Question
A contractor assigned 18 laborers to complete a task in 16
days. Unfortunately, 6 laborers left after 6 days. How many additional days will be required to finish the work?Solution
ATQ,
Let each laborer's efficiency be 'e' units/day
Total work = 18 ├Ч 16 ├Ч e = 288e units
Work done in 6 days = 18 ├Ч 6 ├Ч e = 108e units
Remaining work = 288e - 108e = 180e units
Laborers left = 18 - 6 = 12
Time required = 180e ├╖ (12 ├Ч e) = 15 days
Extra days = 15 - 10 = 5 days
рдпрд╛рдВрддреНрд░рд┐рдХреА рдХрд╛ рдЕрдВрдЧреНрд░реЗрдЬреА рдкрд░реНрдпрд╛рдп рд╣реИ -
рднрд╛рд░рддреАрдп рд░рд┐рдЬрд░реНрд╡ рдмреИрдВрдХ рд╕рднреА рдЕрдиреБрд╕реВрдЪрд┐рдд рдмреИрдВрдХреЛрдВ рдХреЗ рдмреИрдВрдХ рдЦрд╛рддреЗ рд░рдЦрддрд╛ я┐╜...
рдирд┐рдореНрдирд▓рд┐рдЦрд┐рдд рдореЗрдВ рд╕реЗ transferee рдХрд╛ рдкрд░реНрдпрд╛рдп рдирд╣реАрдВ ┬а рд╣реЛрдЧрд╛ ?
A civil suit from its onset till the end faces countless applications by one party or the other.
рдмреИрдВрдХ рд╢рдмреНрджрд╛рд╡рд▓реА┬а рдХреЗ рдЕрдиреБрд╕рд╛рд░┬а account рдХрд╛ рд╣рд┐рдВрджреА рдкрд░реНрдпрд╛рдп рдирд╣реАрдВ рд╣реЛрддрд╛ рд╣реИя┐╜...
рдирд┐рдореНрдирд▓рд┐рдЦрд┐рдд рдЕрдВрдЧреНрд░реЗрдЬреА рд╡рд╛рдХреНрдп рдХрд╛ рд╣рд┐рдВрджреА рдореЗрдВ┬а рд╕рд╣реА рдЕрдиреБрд╡рд╛рдж рдЪреБрдирд┐рдП...
тАЬрдУрдЬреЛрди рдЕрдкрдХреНрд╖рдп рдХрд╛ рд╕рдореНрдмрдВрдз рд╕рдорддрд╛рдк рдордВрдбрд▓ рдореЗрдВ рдзреНрд░реБрд╡реАрдп рднрдВрд╡рд░ рдХреЗ рдирд┐рд░я┐╜...
рдирд┐рдореНрдирд▓рд┐рдЦрд┐рдд рд╡рд┐рдХрд▓реНрдкреЛрдВ рдореЗрдВ рд╕реЗ Counter trade рд╢рдмреНрдж рдХрд╛ рдХреМрди рд╕рд╛ рдкрд░реНрдпрд╛рдп рд╣реЛя┐╜...
There is a need of global movement against unrestricted consumption because this trend causes to degradation of human being.
Convertible рдХрд╛ рд╕рд╣реА рд╣рд┐рдиреНрджреА рдкрд░реНрдпрд╛рдп рдЪреБрдирд┐рдпреЗред