ЁЯУв Too many exams? DonтАЩt know which one suits you best? Book Your Free Expert ЁЯСЙ call Now!


    Question

    A contractor assigned 18 laborers to complete a task in 16

    days. Unfortunately, 6 laborers left after 6 days. How many additional days will be required to finish the work?
    A 5 days Correct Answer Incorrect Answer
    B 4 days Correct Answer Incorrect Answer
    C 3 days Correct Answer Incorrect Answer
    D 7 days Correct Answer Incorrect Answer

    Solution

    ATQ,

    Let each laborer's efficiency be 'e' units/day

    Total work = 18 ├Ч 16 ├Ч e = 288e units

    Work done in 6 days = 18 ├Ч 6 ├Ч e = 108e units

    Remaining work = 288e - 108e = 180e units

    Laborers left = 18 - 6 = 12

    Time required = 180e ├╖ (12 ├Ч e) = 15 days

    Extra days = 15 - 10 = 5 days

    Practice Next
    More Time and work Questions

    Relevant for Exams:

    ask-question