πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      30 labourers are assigned to dig a 4 km canal. After 12

      days, only half of the work is over. Later, 6 more labourers are added. Find in how many days the remaining work will be completed.
      A 25 days Correct Answer Incorrect Answer
      B 18 days Correct Answer Incorrect Answer
      C 10 days Correct Answer Incorrect Answer
      D 12 days Correct Answer Incorrect Answer

      Solution

      ATQ, Let the number of days to complete the remaining work be x. (30 Γ— 12) / (1/2 Γ— 4) = 36x / (1/2 Γ— 4) (30 Γ— 12) / 2 = 36x / 2 180 = 18x x = 10 days

      Practice Next
      More Time and work Questions
      ask-question