Question
A and B alone can complete a work in 15 and 30 days,
respectively. 50% of the work is completed by C in 2x days, and the remaining work is completed by A and B working together in ‘x’ days. Find the time taken by B and C to complete the whole work while working together.Solution
Time taken by A and B to complete the whole work while working together = (15 × 30)/(15 + 30) = 10 days So, x = 10/2 = 5 (Since, 50% of the work is done by A and B together) As, time taken by C to complete 50% of the work = 5 × 2 = 10 days So, time taken by C to complete the entire work = 10 × 2 = 20 days Therefore, time taken by B and C to complete the whole work while working together = (20 × 30)/(20 + 30) = 12 days
What does the agreement between India and Bhutan, involving the establishment of rail links, signify for bilateral relations?
What is the currency of Bhutan besides the Bhutanese Ngultrum?
India will have combined military exercise "Ajeya Warrior – 2017" with which of the following country?
What was the theme of International Museum Day 2024?
What is the length of the Bituminous lane recently laid by NHAI in 105 hours and 33 minutes to enter the Guinness world record?
Which of the following countries was not mentioned as a top investment destination for India's outward FDI?
Which group of workers is eligible for NAMASTE scheme, which is also a key aspect of the banking industry's financial inclusion initiatives?
In which district of India is the first carbon-neutral village being developed?
Which organization manages the Maitri Research and Cultural Partnerships Grants?
What is the total wheat sown area in India according to ISRO's satellite-based estimate?