Question

‘A’ can complete 50% of a work in 6 days. ‘B’ takes 4 days more than ‘A’ to complete the work and ‘B’ is 25% more efficient than ‘C’. ‘A’ started the work alone; on the 2nd day, he is joined by ‘B’ only; on the 3rd day, he is joined by ‘C’ only; on the 4th day, he works alone again, and so on. They worked this way for 6 days. The sum of the time taken to complete the remaining work by ‘A’ alone and by ‘B’ alone is how much percent more/less than that by ‘C’ alone? 

A 35% more
B 40% more
C 45% more
D 30% more
E 50% more