Question
A and B finish a job together in 36 days, while B and C
together finish it in 48 days. The trio completes 75% of the job in 18 days. In how many days will A and C together finish the entire job?Solution
ATQ, Time taken by (A + B + C) for the whole work = 18 / 0.75 = 24 days Let total work = 144 units (LCM of 36, 48, 24) Efficiency of (A + B) = 144 / 36 = 4 units/day Efficiency of (B + C) = 144 / 48 = 3 units/day Efficiency of (A + B + C) = 144 / 24 = 6 units/day Isolate A and C: A = 6 – 3 = 3 units/day C = 6 – 4 = 2 units/day (A + C) = 3 + 2 = 5 units/day Required time = 144 / 5 = 28.8 days
What proportion of AHFCs’ assets under management is in self-construction loans?
In which city is the Moin-ul-Haq Stadium located?
What is the purpose of the Digital Health Incentives Scheme (DHIS) launched under Ayushman Bharat Digital Mission (ABDM)?
The United Nations has declared 2026 as the International Year of:
The primary clinical intent of Russia’s new mRNA cancer vaccine is to:
What was the foundation stone laid by Prime Minister Narendra Modi in Amravati, Maharashtra, in 2024?
What is the total coal reserve estimated in the Namchik-Namphuk coal block in Arunachal Pradesh?
During the upcoming BRICS summit, which five nations are set to join the original founding five (Brazil, Russia, India, China, and South Africa) as new ...
Consider the following statements with respect to a new program been approved by the World Bank -
I.The World Bank has approved a new program to ...
Consider the following statement about Scheduled Banks:
I. Any bank which is listed in the 2nd schedule of the Reserve Bank of India Act, 1934 is...