Question
Alex and John can finish a translation project alone in ‘p’ and ‘q’ days, respectively. The time taken by Alex to complete the project is 50% of the time taken by John. The ratio of efficiency of Alex to that of John is:
More Time and work Questions
- Veer can complete a work in X days and Ayush is 40% more efficient than Veer. If both complete 4/7th of work together and get Rs. 1200 for it, then find di...
- Aman, Arun and Abraham can complete a work in 12, 20 and 24 days respectively. They all start working together. Aman left the work 1 day before its complet...
- A certain number of men, represented as 'm', can finish a task in 40 days. However, if there were 15 additional men, the same task would be completed in 25...
- Farhan and Dev can complete a work alone in 75 days and 90 days respectively. If they work together and earn Rs. 8,250, find Dev’s share.
- A, B and C can complete the whole work in 20 days. A starts the work and works for ‘x’ days while B and C complete the remaining 3/5 of the wor...
- If Pawan can do a piece of work in 6 days and Mantu can complete the same work in 2 days, then in how many days will both of them together complete the wor...
- ‘A’ and ‘B’ can do a piece of work in 10 days and 15 days, respectively. They started working together but ‘A’ left after 3 days. Find the time taken by ‘B...
- 6 men and 6 women can do some work in 3 days. If each man is 200% more efficient than a woman, then find the time taken by 12 men to finish the same work t...
- If Ankit takes four times the time that Ravi takes or five times the time that Sandeep takes to finish a task, and all three working together can complete ...
- P and Q can complete a work in 36 days and 54 days, respectively. P, Q and R together can complete the work in 18 days. If R get a total wage of Rs. 5940 t...