Question
A contractor is hired to complete a road in 40 days and
initially employs 40 workers. After 24 days, he realizes that only one-third of the work has been completed. How many additional workers must he hire to finish the remaining work 4 days ahead of schedule?Solution
Let the number of extra men be ‘m’.
(40 × 24)/(1/3) = [(40 + m) × 12]/(2/3)
m = 120
Prathama Bank was sponsored by SBI
Hornbill Festival is associated with which state?
Income recognition and provisioning guidelines were introduced by RBI in-
Which of the following is the largest organ of the United Nations?
In 1960, _____________, a World Bank arm was established to serve as the Bank's concessional lending arm and provide low and no-cost finance and grants ...
Match the following:
UTI was the first private sector Mutual Fund in IndiaÂ
Which international financial institution did NABARD collaborate with to set up a carbon fund to address climate risks?
When is World Food Day celebrated?
Garima Grehas are primarily established to benefit which of the following groups?