Question
A contractor is hired to complete a road in 40 days and
initially employs 40 workers. After 24 days, he realizes that only one-third of the work has been completed. How many additional workers must he hire to finish the remaining work 4 days ahead of schedule?Solution
Let the number of extra men be ‘m’.
(40 × 24)/(1/3) = [(40 + m) × 12]/(2/3)
m = 120
W is taller than K who is shorter than U. O is taller than D but shorter than K. U is shorter than W. Who is the tallest?
Among F, G, H, I, J and K. H is taller than only F and K and I is shorter than only J and G. If each of them has a different height who among them will ...
What could be the possible height of R?
There are five persons Q, W, R, T and Y of different weights. T is heavier than Q and Y but not the heaviest. W is the lightest. Who among the following...
Who among the following weigh lighter than D?
In a group of four persons B, N, V, and W, V is fatter than only W but not as fat as N. B is also not as fat as N. Who is the leanest person in the group?
What is the weight of T?
There are five friends - D, F, H, M and P who have different heights. F is the tallest. H is taller than only M. P is not as tall as D. Who among the fo...
Who among the following is shorter than I but heavier than I?
Who is the second heaviest person?