Question
A contractor is hired to complete a road in 40 days and
initially employs 40 workers. After 24 days, he realizes that only one-third of the work has been completed. How many additional workers must he hire to finish the remaining work 4 days ahead of schedule?Solution
Let the number of extra men be ‘m’.
(40 × 24)/(1/3) = [(40 + m) × 12]/(2/3)
m = 120
Seed rate required for transplanted pearl millet is
Central Institute of Post Harvest Engineering and Technology (CIPHET) is located at.
What is the latest horticulture production (in million tonnes) for the year 2024-25 as per the 2nd Advance Estimate?
Wh at is India's rank in the global groundnut production?
Pusa giant is a variety of
Which scheme supported the development of the "Rangeen Machhli" app?
Which enzyme is responsible for the ripening process?
During the process of photorespiration which one of these are synthesized
What is the age of enrolment for Pradhan Mantri Kisan Maan Dhyan yojana
Which soil is developed in areas with high temperature and heavy rainfall?