Question
A contractor is hired to complete a road in 40 days and
initially employs 40 workers. After 24 days, he realizes that only one-third of the work has been completed. How many additional workers must he hire to finish the remaining work 4 days ahead of schedule?Solution
Let the number of extra men be ‘m’.
(40 × 24)/(1/3) = [(40 + m) × 12]/(2/3)
m = 120
What will happen when supply elasticity is less than demand elasticity?
Which of the following is not a test related to Heteroscedasticity?
An increase in the expected rate of inflation
Which of the following would shift the ‘Marginal Efficiency of Investment’ (MEI) schedule to the right?
Which of the following is a synonym of "Undistributed Profits"?
Why is the choice of the social discount rate crucial and often contentious in the economic analysis of long-term environmental projects (e.g....
How much additional financing did the World Bank approve to support India’s low carbon transition?
Which of the following is not an example of market failure?
Calculate Domestic Income:
Items
<...During the latest RBI Monetary Policy Committee (MPC) meeting held in August 2024, what was the decision made regarding the repo rate?
Relevant for Exams: