A contractor is hired to complete a road in 40 days and
initially employs 40 workers. After 24 days, he realizes that only one-third of the work has been completed. How many additional workers must he hire to finish the remaining work 4 days ahead of schedule?Solution
Let the number of extra men be ‘m’.
(40 × 24)/(1/3) = [(40 + m) × 12]/(2/3)
m = 120
What is the code for “hard”?
If ‘Hospital’ is called as ‘School’, ‘School’ is called as ‘Temple’, ‘Temple’ is called as ‘Market’, and ‘Market’ is called...
What is the code for ‘say may’ in the given code language?
- In a certain code language, ‘TABLE’ is coded as 14 and ‘CHAIR’ is coded as 10. How will ‘PLATE’ be coded in that language?
In a certain code language, HAIR is written as 72 and PALM is written as 66. What will be the code for THUMB in the same language?
In a certain code language, ‘CALCIUM’ is coded as ‘25’ and ‘FLOWER’ is coded as ‘53’. What is the code of word ‘MEMORIES’ in the sam...
In a certain language ’which have strong legs’, is written as ‘d@f15 s#y12’ h@q18 o@j12, then what does ‘modern house&rsqu...
- In a code language, ‘GARMENTS’ is written as ‘TYINCMGH’ and ‘INFALTION’ is written as ‘GMUYOGGMM’. How will ‘CONSTANT’ be written in th...
In a certain language,
'pl zs ls' means 'conspiracy was hatched',
'uq al bg' means 'would replace him'
'bg kr ls' means ‘him as h...
If ‘DOG’ = 78, then ‘BARK’ = (?)