span >A, B and C can mow a field in 36 days, 72 days and 54 days respectively. All the three began the work together on January 1, 2016, but A left 8 days and C 12 days before the completion of the work. If B took the rest for 4 days, then in how many days the work was finished from the day it started?
More Time and work Questions
- Sachin can complete a job in 15 days. Ankit alone can complete the same job in 10 days. Sachin works for 9 days and then the remaining job is completed by ...
- A can complete 25% of work in five days. And this takes four days more than B to complete the whole work. They started the work together but after X days A...
- A and B together can complete a work in 15 days, while B and C together can complete the same work in 20 days. If A, B, and C together can complete the wor...
- Abhijeet' is 50% less efficient than 'Vivek' and can achieve 25% of the sales target in 8 days.'Chirag' takes 4 days more than 'Vivek' to achieve the targe...
- Karan, Arjun and Krunal alone can complete a work in 50, 75 and 60 days respectively. All of them started working together but after 9 days from start Kara...
- 3 women and 1 girl together can complete a work in 25 days. 2 women and 5 girls can together complete half of the same work in 9 days. Find the time taken ...
- ‘A’ and ‘B’ can do a piece of work in 20 days and 32 days, respectively. If they started the work together and worked on it for 5 days, then find the time ...
- A can do a work in 6 days and B can do it in 12 days. They work together for 2 days. The remaining work is completed by A alone in:
- 8 men can finish a work in 15 days. In how many days can 12 men finish the same work? (Same efficiency)
- A 480-liter blend contains soap and water in a 5:3 ratio. Adding 60 liters of soap and (6u + 30) liters of water changes the ratio to 6:5. Find the ratio o...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)