      Question

      Sachin can complete a job in 15 days. Ankit alone can

      complete the same job in 10 days. Sachin works for 9 days and then the remaining job is completed by Ankit. How many days will it take Ankit to complete the remaining job alone?
      A 5 days Correct Answer Incorrect Answer
      B 8 days Correct Answer Incorrect Answer
      C 6 days Correct Answer Incorrect Answer
      D 4 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Sachin’s 1 day work = 1/15 days
      ∴ Sachin’s 9 days work = 9/15 = 3/5days,
      ∴ Remaining work = 1 - 3/5 = 2/5 part of the work.
      Ankit completes 1 work in 10 days.
      ∴ Ankit will complete 2/5 part of the work in `10xx2/5` = 4 days.
      Alternate Method:
      Sachin Ankit
      Time taken 15 10
      Total work = LCM 30 units
      2 : 3
      Sachin's 9 days work = `2xx9` = 18 units
      So remainning work = 30 - 18 = 12 units which is completed by Ankit alone in = 12/3= 4 days