Question

In government project accounting (like infrastructure projects), revenue recognition may use percentage-of-completion method. Which of the following best describes that method?

A Recognise revenue only on completion
B Recognise a fixed proportion of contract value each year regardless of progress
C Recognise revenue based on proportion of costs incurred to date to total estimated costs
D Recognise revenue only if cash received
E Recognise revenue as equal to billings