Question
A can complete 25% of work in five days. And this takes
four days more than B to complete the whole work. They started the work together but after X days A left and C was 50% as efficient as a joined B and completed the whole work with him. If the total work got completed in 2X days, then find the value of X.Solution
Time taken by A to complete the whole work alone = 20 days. time taken by B To complete the whole work alone = 20-4 = 16 days Let total work = 80 unit (LCM of 20 and 16) Efficiency of A= 80/20 = 4 units/day Efficiency of B = 80/ 16 = 5 Units/day. Efficiency of C = 0.5*4 =Â 2 units/ day Also B&C together worked for= X days. (4+5)*x+(5+2)*x = 80 16x=80 X=5 Therefore efficiency of D,= (X + 11)= 16 units / day Required. Time taken. = 80/16 = 5 days
Pusa Deepali is a variety of:
Capitate type of antenna are found in _____
Bud scales (cataphylls) are_____ designed for protecting buds (apical or axillary).
Part of the cell wall of endodermal cells prevents water from moving into the cell is calledÂ
Eugenol is the important chemical content of:
The typical pH value of the midgut in most insects is closest to which of the following values?
Microorganisms used for suppression of plant diseases are called as ____
Judicious removal of plant part to obtain better and qualitative yield is termed asÂ
Chlorophyll is the major pigment present in leaves ,Which element is known as a ‘constituent of chlorophyll’?
Out of the following quantity, which is required to irrigate 1.0 ha land area with 50mm depth of irrigation?