Question
βAβ and βBβ can do a piece of work in 20 days
and 32 days, respectively. If they started the work together and worked on it for 5 days, then find the time taken by βBβ alone to complete the remaining work.Solution
Let total amount of work be 160 unitsΒ Efficiency of βAβ = 160/20 = 8 units/day Efficiency of βBβ = 160/32 = 5 units/day Amount of work done by βAβ and βBβ together in 5 days = (8 + 5) Γ 5 = 65 units Time taken by B to complete remaining work = (160 β 65)/5 = 19 days
How can you add a transition effect between slides in PowerPoint?
What is the purpose of the "Slide Show" tab in PowerPoint?
Which feature in Microsoft Word allows you to create personalized letters or emails by automatically inserting individual names and addresses from a dat...
How can you crop an image in PowerPoint?
Eena Khande is creating her project report as a document and is interested in typing the same in an easy-to-use software with facility of formatting pag...
In Windows operating system it is the long horizontal bar at the bottom of a screen.
Which formula is used to join text from two cells in a spreadsheet?
Which of the following is the correct file extension of Portable document format?
Which option in Microsoft Word allows you to create a duplicate copy of the selected text or object?
'FIND' option is available under which of the following menu?