βAβ and βBβ can do a piece of work in 20 days
and 32 days, respectively. If they started the work together and worked on it for 5 days, then find the time taken by βBβ alone to complete the remaining work.Solution
Let total amount of work be 160 unitsΒ Efficiency of βAβ = 160/20 = 8 units/day Efficiency of βBβ = 160/32 = 5 units/day Amount of work done by βAβ and βBβ together in 5 days = (8 + 5) Γ 5 = 65 units Time taken by B to complete remaining work = (160 β 65)/5 = 19 days
Which certification is required for the export of organic products?
Given below are two statements:
Statement I: Kisan Call Centers are providing agricultural advice and information to the farmers across the count...
Match list I with list II
Which of the following is a major cause of increasing ocean acidification?
Which of the following is not the classified form of conjugated proteins?
A company is said to be unicorn company when the valuation reaches ______
What is the recommended fluoride concentration in drinking water to protect teeth against decay?
What is the sex ratio in monoecious cucurbits like bitter gourd?
Isolation distance for producing foundation seed of bajra hybrid
Among the following irrigation systems, which is most efficient and economical?Β