πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!


    Question

    A can finish a work in 12 days and B can finish the same

    work in 18 days. They work together for 4 days and then B leaves. In how many more days can A alone finish the remaining work?
    A 3β…“ days Correct Answer Incorrect Answer
    B 5β…“ days Correct Answer Incorrect Answer
    C 7β…“ days Correct Answer Incorrect Answer
    D 2β…“ days Correct Answer Incorrect Answer

    Solution

    ATQ, Take total work = LCM(12, 18) = 36 units. A’s rate = 36/12 = 3 units/day B’s rate = 36/18 = 2 units/day Together, in 1 day = 5 units. In 4 days, work done = 5 Γ— 4 = 20 units. Remaining work = 36 βˆ’ 20 = 16 units. A alone does 3 units/day. Days needed = 16/3 = 5β…“ days.