A can finish a work in 12 days and B can finish the same
work in 18 days. They work together for 4 days and then B leaves. In how many more days can A alone finish the remaining work?Solution
ATQ, Take total work = LCM(12, 18) = 36 units. A’s rate = 36/12 = 3 units/day B’s rate = 36/18 = 2 units/day Together, in 1 day = 5 units. In 4 days, work done = 5 × 4 = 20 units. Remaining work = 36 − 20 = 16 units. A alone does 3 units/day. Days needed = 16/3 = 5⅓ days.
_________ defeated Mahmud Khilji and erected the tower of victory (Vijay Stambha) in Chittorgarh.
Who among the following is the author of “Principles of Political Economy”?
The Destructive Insects and Pests Act came into force in the year:
When we divide NNP (Net national product) by the total population of a nation we get _____.
What is the name of the Apple's virtual assistant?
As per Section 2 of the Antiquities and Art Treasures Act, 1972, ‘Antiquities’ include 'any manuscript, record or other document which is of scienti...
The FAME-II scheme is designed to provide incentives to manufacturers for the production of electric vehicles (EVs) and to promote the development of n...
What is the unit of measurement for optical power of the lens?
______ was one of the first Indian rulers to lead an armed rebellion against the British East India Company in 1824 against the implementation of the Do...
Who among the following serves as the Guardian of Fundamental Rights?