Question
A can finish a work in 12 days and B can finish the same
work in 18 days. They work together for 4 days and then B leaves. In how many more days can A alone finish the remaining work?Solution
ATQ, Take total work = LCM(12, 18) = 36 units. A’s rate = 36/12 = 3 units/day B’s rate = 36/18 = 2 units/day Together, in 1 day = 5 units. In 4 days, work done = 5 × 4 = 20 units. Remaining work = 36 − 20 = 16 units. A alone does 3 units/day. Days needed = 16/3 = 5⅓ days.
Which of the following is the implementing agency of Pradhan Mantri Bhartiya Janaushadhi Pariyojana (PMBJP)?
Who are "Corporate Mitras" as defined in the budget speech?
The Karnataka government has signed a Letter of Intent (LoI) with Foxconn, a major iPhone assembler for tech giant Apple, to undertake two marquee proje...
Recently In July 2023, PM inaugurated how many EMRS school in Rajasthan?Â
Which museum in India was inaugurated by Union Minister Gajendra Singh Shekhawat in collaboration with the Aga Khan Trust for Culture? Â
LEO1, an edu-fintech startup has introduced prepaid ID cards for students and educational institutions that is supported by MasterCard which is devoid o...
Which bank is associated with an ‘open loop ticketing system’?
Consider the following statements regarding the April trade deficit in India:
Statement 1: The trade deficit was primarily driven by a significan...
Which Union Minister released the Assessment of Logistics Cost in India report in New Delhi?
What is the new deposit insurance premium framework approved by the Reserve Bank of India (RBI) to replace the flat-rate system?