Question

Virat can do a piece of work in 30 days and Sachin can do the same work in 45 days. If Virat works for 5 days and got Rs. 2100, and the remaining work will completed by Sachin, then how much rupee Sachin earned?

A Rs.9600
B Rs.12600
C Rs.10800
D Rs.10500
E Rs.13500