Question
Virat can do a piece of work in 30 days and Sachin can do the same work in 45 days. If Virat works for 5 days and got Rs. 2100, and the remaining work will completed by Sachin, then how much rupee Sachin earned?
More Time and work Questions
- P and Q can complete a work in 30 days and 45 days, respectively. P, Q and R together can complete the work in 15 days. If R get a total wage of Rs. 5400 t...
- A and B working together, can do a piece of work in 4(1/2) hours. B and C working together can do it in 3 hours. C and A working together can do it in 2(1/...
- 'Sumit' can complete (3/8) of a job in 24 days, where as 'Sumit' and 'Tarun' together can finish it in 16 days. Calculate the time 'Tarun' needs to complet...
- Amit and Anaya can complete a task together in 20 days. If Anaya is 150% more efficient than Amit, how many days will Anaya alone take to finish the task?
- 3 workers paint 5 rooms in 8 days. How many workers are needed to paint 10 rooms in 6 days?
- 20 boys can dig a pit in 15 days, while 5 men can dig the same pit in 6 days. In how many days will 10 boys and 1 man together dig the pit?
- A can complete a work in 12 days and B in 18 days. They work together for 6 days, then B leaves. How many total days to finish the work?
- Ramesh needs half the time that Suresh needs to complete a job. Suresh and Tarun together complete it in 27 days, whereas Ramesh and Tarun take 18 days. Ho...
- 16 men or 24 women can complete a piece of work in 36 days. A man and a woman together complete the work and receive a total wage of Rs. 9,600. Find the di...
- A can complete a piece of work in 10 days. B in 15 days and C in 20 days. A and C worked together for two days and then A was replaced by B. In how many da...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)