Question
A, B, and C can individually complete a task in 20
days, 15 days, and 10 days, respectively. B and C begin the task and work together for 3 days, after which both of them leave. How many days will it take for A to finish the remaining work by themselves?Solution
Let the total work be 60 units (L.C.M of 20, 15 and 10) Efficiency of A = 60/20 = 3 units/day Efficiency of B = 60/15 = 4 units/day Efficiency of C = 60/10 = 6 units/day Amount of work completed by B and C in 3 days = (6 + 4) × 3 = 30 units Time taken by A to complete the remaining work alone = (60 – 30)/3 = 10 days
More Time and work Questions
- Which letter and number cluster will replace the question mark (?) to complete the given series?
LT6, KU12, IW24, FZ48, ____ - Which letter-cluster will replace the question mark (?) in the following series?
RGV, UME, ?, AYW, DEF - Which letter-cluster will replace the question mark (?) in the following series?
NPQR, OORQ, PNSP, ____, RLUN - A series is given with one term missing. Choose the correct alternatives from the given ones that will complete the series.
57, 59, 56, 61, 54, ___ - Select the number from among the given options that can replace the question mark (?) in the following series.
17, 18, 22, 31, 47, ___