Question
A, B, and C can individually complete a task in 20
days, 15 days, and 10 days, respectively. B and C begin the task and work together for 3 days, after which both of them leave. How many days will it take for A to finish the remaining work by themselves?Solution
Let the total work be 60 units (L.C.M of 20, 15 and 10) Efficiency of A = 60/20 = 3 units/day Efficiency of B = 60/15 = 4 units/day Efficiency of C = 60/10 = 6 units/day Amount of work completed by B and C in 3 days = (6 + 4) × 3 = 30 units Time taken by A to complete the remaining work alone = (60 – 30)/3 = 10 days
In India, the highest cricket ground above sea level lies in which state?
What is BREXIT?
Murudeshwar Temple is situated on Kanduka Giri in the state of ___________.
As per the Constitution of India, the subject of 'livestock and animal husbandry' is included in the:
State Bank of India (SBI) has partnered with housing finance companies (HFCs) to provide affordable home loans to small home buyers in the country. Name...
Wing Commander Gajanand Yadava was awarded the ‘Tenzing Norgay National Adventure Award 2019’ in:
In the recently launched NAVYA scheme under Viksit Bharat@2047, what does the letter ‘N’ stand for?
Purandara Dasa is popularly known as the _________.
The study of sound & sound waves-
In which state is Vishakhapatnam Port located?