Question
A, B, and C can individually complete a task in 20
days, 15 days, and 10 days, respectively. B and C begin the task and work together for 3 days, after which both of them leave. How many days will it take for A to finish the remaining work by themselves?Solution
Let the total work be 60 units (L.C.M of 20, 15 and 10) Efficiency of A = 60/20 = 3 units/day Efficiency of B = 60/15 = 4 units/day Efficiency of C = 60/10 = 6 units/day Amount of work completed by B and C in 3 days = (6 + 4) Γ 3 = 30 units Time taken by A to complete the remaining work alone = (60 β 30)/3 = 10 days
Mahalanobis model is β
Consider an economy described by the following equations:
C = 100 + 0.6 ∗ (Y − T) (consumption function)
I = 200 − 10...
If quantities of all commodities change in the same proportion then
Let X and Y represent prices in Rs of a commodity in Kolkata and Mumbai respectively. It is given X(bar) = 65, Y(bar) = 67, standard deviation...
The price elasticity of demand for good X is known to be twice that of good Y. Price of X falls by 5% while that of good Y rises by 5%. What is the perc...
In a time-series forecasting problem, if the seasonal indices for quarters 1, 2, and 3 are 0.80, 0.90, and 0.95 respectively. What can you say...
What is the probability of getting atleast one head if three unbiased coins are tossed?
Which of the following institutions is primarily concerned with promoting stability in the international monetary system through surveillance and lending?
Refer to the below table and calculate the NNPmp
Which of the following could be a remedy for Multicollinearity Problem?