Question
A and B together can complete a piece of work in 12
days. A alone can complete the work in 20 days. A starts the work and is joined by B after 5 days. How many more days will they take to complete the remaining work?Solution
Total work = LCM of 12 and 20 = 60 units. Efficiency of A = 60 ÷ 20 = 3 units/day. Efficiency of A and B together = 60 ÷ 12 = 5 units/day. Work done by A in 5 days = 5 × 3 = 15 units. Remaining work = 60 - 15 = 45 units. Time taken by A and B together to complete remaining work = 45 ÷ 5 = 9 days. Correct Option: d) 9 days
Recently REC Ltd and Power Finance Corporation have signed a MoU to provide financial assistance to set up a thermal power station by SJVN Thermal Priv...
Indian Renewable Energy Development Agency (IREDA), has signed a performance-based Memorandum of Understanding (MoU) with the Ministry of New and Renewa...
Which Payments Bank has launched an eco-friendly debit card for its customers with savings bank accounts, underlining the company's commitment to sustai...
- What is the estimated Consumer Price Index (CPI) inflation rate for FY 2025–26?
What was the theme of World Happiness Day 2025?
Identify the correct statements about India’s textile and apparel exports in FY25:
1. Total exports amounted to USD 21.358 billion during April...
Who has been elected as the 11th President of the Asian Development Bank (ADB)?
- Which ministry signed an MoU with the Indian Navy to revive an ancient shipbuilding technique in 2023?
Which state police recently launched the digital platform 'Trinetra' App 2.0?
What is the rank of India in the Global Innovation Index 2024?