      Question

      An elephant can do a work as fast as two horses β€˜A’

      and β€˜B’ can do it by working together. If horse β€˜A’ alone can complete the work in 40 hours and horse β€˜B’ in 60 hours, then find the time taken by elephant to complete the work.
      A 12 hours Correct Answer Incorrect Answer
      B 10 hours Correct Answer Incorrect Answer
      C 18 hours Correct Answer Incorrect Answer
      D 24 hours Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Let the total work = 120 units Efficiency of horse who can complete the work in 40 hours = 120/40 = 3 units/hour Efficiency of horse who can complete the work in 60 hours = 120/60 = 2 units/hour Therefore, time taken by both horses to complete the work together = 120/(3 + 2) = 24 hours Therefore, time taken by the elephant to complete the work = 24 hours