Question
Abhay, Beer, and Tittu have individual work completion times of 12 days, 24 days, and 36 days, respectively. They Started working together on a task. After working for only 4 days, Abhay ceased working, and Tittu quit 6 days before the job's conclusion. How many days were needed to complete the job?
More Time and work Questions
- X, Y, and Z alone can complete a language translation in 60, 90, and 36 days respectively. They started working together, but after 5 days, Z left the job,...
- If Arjun can complete his work in 28 days by working 4 hours a day, how many hours a day should he work to finish the same work in 16 days?
- X men can complete the piece of work in 45 days and (X + 46) men can complete the same work in 23 days less than that of days taken by X men. Find the valu...
- 5 men and 6 women can do some work in 3 days. If each man is 50% more efficient than a woman, then find the time taken by 9 men to finish the same work tog...
- When working alone, Ansh takes 12 more days than time taken by Ansh and Balu together to finish certain work. If Ansh is 50% more efficient than Balu, then...
- (x) men can do some work in 42 days. If 10 more men added then the work would have been completed in 30 days, then in how many days (x+45) men can do the s...
- Sonal completed 30% of work alone and left the remaining work for Vinod who completed it in 28 days. If the total work got completed in 40 days, then find ...
- A can finish a piece of work in 10 days and B can finish it in 15 days. If both work together, in how many days will the work be completed?
- A, B, and C are hired to complete a task. A and B together can finish the work in 12 days, B and C together in 15 days, and A and C together in 20 days. Ho...
- ‘P’ is 20% more efficient than ‘Q’. ‘P’ can do a piece of work in 15 days. They begin the work together, but ‘Q’ leaves after 6 days. The rest of the work ...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)