Question
In a factory, there are 3 machines. Machine A completes a task in 8 days, Machine B completes it in 12 days, and Machine C completes it in 15 days. If all machines are working together, how long will they take to complete the task?
More Time and work Questions
- Amit manages to reach 25% of a sales goal in 6 days, whereas Geeta can achieve 40% of the same goal within the same timeframe. How long would it take for b...
- 24 male working 12 hours per day can finish a piece of work in 30 days, while 36 female working 8 hours per day can finish the same work in 60 days. Which...
- Two individuals, P and Q, can complete a task in (x + 6) days and (x + 3) days, respectively. Another individual, S, is capable of completing 25% of the sa...
- Elvish is 10% more efficient than Fatima. Elvish completes typing 198 pages in 18 hours. Find how many pages Fatima can type in 5 hours.
- A and B together, B and C together and A and C together can complete a piece of work in 14 days, 15 days and 18 days respectively. Find the ratio of the ef...
- Aisha and Neel can complete a job alone in 66 days and 99 days respectively. Working together, they earn a total wage of Rs. 11,550. How much does Aisha re...
- ‘P’ can complete 80% of a task in 32 days and ‘Q’ can do 60% of the task in 54 days. If ‘P’, ‘Q’, and ‘R’ all work together, they can complete the full tas...
- A can complete a work in 18 days , B in 24 days , and C in 36 days . A starts the work alone and works for 4 days . Then B joins him, and after 3 more...
- 50 workers working 6 hours a day take 18 days to complete a task. How many workers working for 5 hours a day are needed to complete four times the given ta...
- A and B can complete a piece of work in 12 days and 15 days respectively. They start working together, but after 4 days, A leaves. In how many more days wi...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)