Question
In a factory, there are 3 machines. Machine A completes
a task in 8 days, Machine B completes it in 12 days, and Machine C completes it in 15 days. If all machines are working together, how long will they take to complete the task?Solution
Rate of work of A = 1/8, B = 1/12, C = 1/15 Combined rate of work = 1/8 + 1/12 + 1/15 LCM of 8, 12, and 15 = 120 Combined rate = (15 + 10 + 8)/120 = 33/120Â Time taken = 40/11 days Correct Option: a
In addition to financial support, what other incentives are provided by the PM Vishwakarma scheme?
Ministry of Agriculture and Farmers’ Welfare established SARTHI Portal in collaboration with which of the following organisations?
Which of the following is NOT a core focus area of the "Cities as Growth Hubs" initiative within the 2024-25 Union Budget?
Education is in which list of Seventh Schedule of the Indian Constitution?
India Industrial Land Bank (IILB) is ______________.
Which of the following is not a commodity board under the Ministry of Commerce?
Through which of the following ways the PMKSY Scheme is implemented?
Consider the following Statements about Digital India Initiative.
(I) Its main objective is to prepare India for a knowledge future
(II) I...
The difference between GDP and GNP is due to:
What are the eligibility criteria for the "Top Class Education for SCs" sub-scheme?