Question

A and B can complete a task in 6 days working together. A alone works twice as fast as
B. If A works alone for 2 days and B finishes the rest, how many more days does B take?

A 48 days Correct Answer Incorrect Answer
B 22 days Correct Answer Incorrect Answer
C 14 days Correct Answer Incorrect Answer
D 32 days Correct Answer Incorrect Answer

Solution

ATQ,

A = 2B rate

→ together 1/6

→ (2B + B)/6 = 1

→ 3B = 1/6

→ B = 1/18, A = 1/9 Work done by A in 2 days = 2/9 → Remaining = 7/9 → Time by B = (7/9) ÷ (1/18) = 14 days

Practice Next
More Time and work Questions
ask-question