πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      A and B can complete a task in 6 days working together.

      A alone works twice as fast as B. If A works alone for 2 days and B finishes the rest, how many more days does B take?
      A 48 days Correct Answer Incorrect Answer
      B 22 days Correct Answer Incorrect Answer
      C 14 days Correct Answer Incorrect Answer
      D 32 days Correct Answer Incorrect Answer

      Solution

      ATQ,

      A = 2B rate

      β†’ together 1/6

      β†’ (2B + B)/6 = 1

      β†’ 3B = 1/6

      β†’ B = 1/18, A = 1/9 Work done by A in 2 days = 2/9 β†’ Remaining = 7/9 β†’ Time by B = (7/9) Γ· (1/18) = 14 days

      Practice Next
      ask-question