Question
Ravi, Sohan, and Mohan can complete a certain task
individually in 18 days, 24 days, and 30 days, respectively. They all started working together, but after 6 days, Ravi and Mohan left, leaving Sohan to finish the remaining work alone. Determine the total number of days required to complete the entire task under these conditions.Solution
ATQ,Let total work be 360 units. {LCM (18, 24, and 30)}Efficiency of ‘Ravi’ = (360/18) = 20 units/dayEfficiency of ‘Sohan’ = (360/24) = 15 units/dayEfficiency of ‘Mohan’ = (360/30) = 12 units/dayWork completed in 6 days = {(20 + 15 + 12) × 6} = 282 unitsWork remaining = 360 – 282 = 78 unitsSo, time taken by ‘Sohan’ alone to complete the remaining work = {(360 – 282)/15} = 5.2 daysTherefore, total time taken to complete the work = (6 + 5.2) = 11.2 days
What is the theme for World Day for Safety and Health at Work 2025?
What was the budget allocation for the newly approved 'Mission Mausam' by the Indian government?
Which state has the largest castor cultivation area in India?
The Union Cabinet approved Rs 76,000 crore production linked incentive (PLI) scheme for _____________.
Which Indian state enacted the 'Aparajita' anti-rape legislation amidst extensive political discussions?
What was India's foreign exchange reserve as of September 27, 2024, making India the fourth country to surpass this milestone?
Recently a Kashmiri film (entirely shot and produced in the valley) was released after 45 years. Name the film:
Which section of the Sutta Pitaka is known for its collection of minor sermons and doctrines of Buddha?
What is the target set by the National Green Hydrogen Mission for green hydrogen production per year by 2030?
As part of its e-mobility push, how many EV charging stations does India plan to set up under the PM E-Drive scheme?