Ravi, Sohan, and Mohan can complete a certain task
individually in 18 days, 24 days, and 30 days, respectively. They all started working together, but after 6 days, Ravi and Mohan left, leaving Sohan to finish the remaining work alone. Determine the total number of days required to complete the entire task under these conditions.Solution
ATQ,Let total work be 360 units. {LCM (18, 24, and 30)}Efficiency of ‘Ravi’ = (360/18) = 20 units/dayEfficiency of ‘Sohan’ = (360/24) = 15 units/dayEfficiency of ‘Mohan’ = (360/30) = 12 units/dayWork completed in 6 days = {(20 + 15 + 12) × 6} = 282 unitsWork remaining = 360 – 282 = 78 unitsSo, time taken by ‘Sohan’ alone to complete the remaining work = {(360 – 282)/15} = 5.2 daysTherefore, total time taken to complete the work = (6 + 5.2) = 11.2 days
What is the average number of Bikes manufactured by companies Hero, Bajaj and TVS?
What is the difference between average numbers of women went to cinema hall B, D and E together and number of men went to cinema hall A?
Find the difference between the total numbers of moisturizers sold on Tuesday and Thursday.
Read the table given below and answer the following question given below.
Number of Students in Five Schools
A shopkeeper bought 120 kg of sugar at ₹40 per kg and 150 kg at ₹30 per kg. If he sells the entire quantity at ₹45 per kg, what is his total profit?
Number of wallets sold by A on Tuesday is what% of total number of wallet sold by the same store on all the days?
Find the number of mobile phones sold by shopkeeper B.
In 2016, 23% of the number of students who did not appeared for the exam from city E. However each year number of students increases by 10% in number. W...
Answer the questions based on the information given below.
The line graph given below shows the number of scooters sold by different showrooms ...
Line graph given below shows the goal scored by different players in a football match.