Question
Ravi, Sohan, and Mohan can complete a certain task
individually in 18 days, 24 days, and 30 days, respectively. They all started working together, but after 6 days, Ravi and Mohan left, leaving Sohan to finish the remaining work alone. Determine the total number of days required to complete the entire task under these conditions.Solution
ATQ,Let total work be 360 units. {LCM (18, 24, and 30)}Efficiency of ‘Ravi’ = (360/18) = 20 units/dayEfficiency of ‘Sohan’ = (360/24) = 15 units/dayEfficiency of ‘Mohan’ = (360/30) = 12 units/dayWork completed in 6 days = {(20 + 15 + 12) × 6} = 282 unitsWork remaining = 360 – 282 = 78 unitsSo, time taken by ‘Sohan’ alone to complete the remaining work = {(360 – 282)/15} = 5.2 daysTherefore, total time taken to complete the work = (6 + 5.2) = 11.2 days
How many tribal-dominated districts are covered under the Dharti Aaba Janbhagidari Abhiyan?
What was the theme of the 9th India Mobile Congress (IMC) 2025 announced by Jyotiraditya Scindia?
How much loan amount has ADB signed with the Government of India for development projects across states?
As per government accounts up to August 2025, how much was spent on interest payments?
What is “fossil fuel depletion”?
According to Mahatma Gandhi, which symbol represented the unity, economic independence, and equality of Indian society?
What initiative by MoPR and IIM Ahmedabad aims to train Panchayats on revenue generation?
Which organization co-hosted the DialogueNEXT Conference 2025 in New Delhi alongside CIMMYT and ICAR?
Why is the India-EU Trade and Technology Council significant in bilateral relations?
Which city is set to host the 2025 Asian Youth Para Games?