Question
Ravi, Sohan, and Mohan can complete a certain task
individually in 18 days, 24 days, and 30 days, respectively. They all started working together, but after 6 days, Ravi and Mohan left, leaving Sohan to finish the remaining work alone. Determine the total number of days required to complete the entire task under these conditions.Solution
ATQ,Let total work be 360 units. {LCM (18, 24, and 30)}Efficiency of ‘Ravi’ = (360/18) = 20 units/dayEfficiency of ‘Sohan’ = (360/24) = 15 units/dayEfficiency of ‘Mohan’ = (360/30) = 12 units/dayWork completed in 6 days = {(20 + 15 + 12) × 6} = 282 unitsWork remaining = 360 – 282 = 78 unitsSo, time taken by ‘Sohan’ alone to complete the remaining work = {(360 – 282)/15} = 5.2 daysTherefore, total time taken to complete the work = (6 + 5.2) = 11.2 days
What is the purpose and potential impact of the "Saral" portal launched by the Union Government of India to improve the ease of living for the common man?
After the abolition of industrial licensing in India in 1991, ____________ is one of the few industries for which it is mandatory to obtain an industria...
In which of the following ways can 1 Volt be expressed?
In which type of tax is the marginal tax rate higher than the average tax rate?
In MS Word, which feature allows you to create different headers and footers for odd and even pages in a document?
Which among the following organizations releases Habitat's World Cities Report?
Which of the following cyclone hit the countries USA and Canada recently?
The Sustainable Development Goals (SDG) performance index measures the performance of how many countries?
What is the maximum deposit amount insured by the DICGC?
Which of the following type of rays does NOT penetrate Earth's atmosphere?