Question
Ravi, Sohan, and Mohan can complete a certain task
individually in 18 days, 24 days, and 30 days, respectively. They all started working together, but after 6 days, Ravi and Mohan left, leaving Sohan to finish the remaining work alone. Determine the total number of days required to complete the entire task under these conditions.Solution
ATQ,Let total work be 360 units. {LCM (18, 24, and 30)}Efficiency of ‘Ravi’ = (360/18) = 20 units/dayEfficiency of ‘Sohan’ = (360/24) = 15 units/dayEfficiency of ‘Mohan’ = (360/30) = 12 units/dayWork completed in 6 days = {(20 + 15 + 12) × 6} = 282 unitsWork remaining = 360 – 282 = 78 unitsSo, time taken by ‘Sohan’ alone to complete the remaining work = {(360 – 282)/15} = 5.2 daysTherefore, total time taken to complete the work = (6 + 5.2) = 11.2 days
Consider the following statements:Â
1. The duration of the monsoon decreases from southern India to northern India.
2. The amount of annu...
The other name of ‘Swaraj Island’ is ________.
Which Indian state is Uttar Pradesh's neighbor to the west?
Which river of Peninsular India does not flow into the Arabian Sea?
The term "Escrow account" generally refers to:
Arrange the following mountain ranges from North to South.
1. Vindhya Range
2. Ajanta range
3. Satpura range
4. Nal...
Which mountain range forms the northern boundary of the Indian subcontinent?
When does lunar eclipse occur?
Who is operating the Noida International Airport?
Which is the largest uranium producing country in the world?