Question
A team of 15 workers was assigned to complete a task in 30
days. After working together for 20 days, they discovered that only half of the work had been completed. To finish the remaining work within the original deadline, how many additional workers need to be hired?Solution
Let the total work = 15 × 30 = 450 units
Work done in 20 days = 450/2 = 225 units
Work left = 450 – 225 = 225 units
Now, the work done in 20 days has to be completed in 10 days.
So, (15 × 20) = (15 + x) × 10
300 = 150 + 10x
x = 15
So, 15 more men are required to complete the work on time.
A graduate of Fergusson college he was one of the recipients of Shyamji Krishnavarma’s fellowship. He was deeply inspired by the ideas of Mazzini and ...
Consider the following statements with reference to the organizations formed during late 19th century:
1. The Poona Sarvajanik Sabha was founded ...
The Indian Home Rule Society was established in which year?
He developed a spiritual practice called Internal Yoga. One of his close spiritual collaborator, Mirra Alfassa, founded an ashram in his name in Pondic...
The "History of British India" is a three-volume work by ________.
In the context of Indian history, what was the Dandi March
Consider the following statements with reference to the Ghadar Party:
1. It was founded by expatriate Indians to overthrow British rule in Ind...
Which one of the following policies was used by the British to keep Napoleon at a distance?Â
In the context of the decline in the revolutionary, consider the following statements:
1. Gandhi’s ideas of Mass Nationalism
2. Mor...
Who led the English forces to victory in the Battle of Bedara against the Dutch in Bengal, securing British dominance in the region?