Question
A team of 15 workers was assigned to complete a task in 30
days. After working together for 20 days, they discovered that only half of the work had been completed. To finish the remaining work within the original deadline, how many additional workers need to be hired?Solution
Let the total work = 15 × 30 = 450 units
Work done in 20 days = 450/2 = 225 units
Work left = 450 – 225 = 225 units
Now, the work done in 20 days has to be completed in 10 days.
So, (15 × 20) = (15 + x) × 10
300 = 150 + 10x
x = 15
So, 15 more men are required to complete the work on time.
In these questions two sentences are given with blanks in them and you have to choose an appropriate word from the given options that can fill both the...
You are provided with a sentence with one word missing, denoted by a blank. You are presented with four options (A), (B), (C) and (D), identify which of...
Fill in the blanks by choosing the correct connector from the alternatives given below each sentence.
____ you have any doubt, please ask me....
While hiking the mountains of Nepal, a British Hiker irked a tea seller by bargaining for what she thought was steeply priced tea. At 150 Nepalese Rupee...
Educate your children and let them learn to live with ________.
(A) elevation (B) dignity (C) respect ...
Fill in the blanks using the correct tense of the verbs given in brackets and choose the right answer from among the options given below them.
Turning around a __________ ship is never easy.
(A) large
(B) small
(C) tiny
(D) huge
- Given below is a sentence with one blank. Below the sentence are given four words among which one word might fill the blank. If none of the words fill the ...
Despite the uninspiring weather, the city was ……….. with a youthful ………..
In the following sentences, two words are omitted. Choose the correct option that can fill the blanks both contextually and grammatically.
Th...