Question
A team of 15 workers was assigned to complete a task in 30
days. After working together for 20 days, they discovered that only half of the work had been completed. To finish the remaining work within the original deadline, how many additional workers need to be hired?Solution
Let the total work = 15 × 30 = 450 units
Work done in 20 days = 450/2 = 225 units
Work left = 450 – 225 = 225 units
Now, the work done in 20 days has to be completed in 10 days.
So, (15 × 20) = (15 + x) × 10
300 = 150 + 10x
x = 15
So, 15 more men are required to complete the work on time.
In Excel typical worksheet has …. Number of columns
A half byte is know is
While studying about computer, we may came to know about the term QDR. Expand QDR?
A saved document is referred to as _________.
Word processing, spreadsheet, and photo-editing are examples of which type of software?
To print a document which shortcut is used?
Which of the following is a form of malware that encrypts a victim's files?
Which of the following Internet protocol specifies how data is exchanged over the Internet and how it should be broken into IP packets?
What happens when you press the "Insert" key on the keyboard?
Which sorting algorithm has a worst-case time complexity of O(n²)?