Question
A team of 15 workers was assigned to complete a task in 30
days. After working together for 20 days, they discovered that only half of the work had been completed. To finish the remaining work within the original deadline, how many additional workers need to be hired?Solution
Let the total work = 15 × 30 = 450 units
Work done in 20 days = 450/2 = 225 units
Work left = 450 – 225 = 225 units
Now, the work done in 20 days has to be completed in 10 days.
So, (15 × 20) = (15 + x) × 10
300 = 150 + 10x
x = 15
So, 15 more men are required to complete the work on time.
Systemically Important NBFCs are:
Which of the following is NOT a valid purpose for creating a trust under the Indian Trusts Act, 1882?Â
Which of the following statements is/are not correct in regards to the service sector in Economic Survey 2022-23?
1.RBI estimated 6.8% of retail ...
According to Rule 12 of the IFSCA (Banking) Regulation, 2020 cash transactions in foreign currency accounts __________.
Which of the following is not one of the features of a Global Financial Centre?
Which of the following reports are on the rankings of financial centers in the world?
The highest surcharge rate of 37% on income above 5 crores shall be reduced to ______ % under the new tax regime.
On which date was the India International Bullion Exchange IFSC Limited (IIBX) launched?
Which of the following are under the 6 Challenges to Global Growth, according to the Economic Survey 2022-23?
1.   Synchronized policy rat...
What kind of infrastructure gives the highest impetus for a successful global financial center?