A team of 15 workers was assigned to complete a task in 30
days. After working together for 20 days, they discovered that only half of the work had been completed. To finish the remaining work within the original deadline, how many additional workers need to be hired?Solution
Let the total work = 15 × 30 = 450 units
Work done in 20 days = 450/2 = 225 units
Work left = 450 – 225 = 225 units
Now, the work done in 20 days has to be completed in 10 days.
So, (15 × 20) = (15 + x) × 10
300 = 150 + 10x
x = 15
So, 15 more men are required to complete the work on time.
 Which of the following describes a situation where an economic change satisfies the Kaldor-Hicks Criterion but fails the Scitovsky Paradox (Double Cri...
For the following demand curve, Q=10P-2 , calculate the profit made by the monopolist when Marginal cost is Rs.2
For Cobb-Douglas production function the elasticity of substitution is
Which stage in Rostow's Stages of Economic Growth is characterized by the expansion of modern technology across all sectors and the development of new, ...
Type II error occurs when
In a futures contract, marking-to-market refers to:
For fixed proportion production function, the elasticity of substitution is
If the money supply grows 5 per cent, and real output grows 2 per cent, prices should rise by
The fiscal deficit is the difference between the government’s total expenditure and its total receipts excluding ______
Calculate NNPfc from the following data:
(in Rs crores)