Question
A team of 15 workers was assigned to complete a task in 30
days. After working together for 20 days, they discovered that only half of the work had been completed. To finish the remaining work within the original deadline, how many additional workers need to be hired?Solution
Let the total work = 15 × 30 = 450 units
Work done in 20 days = 450/2 = 225 units
Work left = 450 – 225 = 225 units
Now, the work done in 20 days has to be completed in 10 days.
So, (15 × 20) = (15 + x) × 10
300 = 150 + 10x
x = 15
So, 15 more men are required to complete the work on time.
Under the revised RBI instructions on hedging foreign exchange risk, users are allowed to hedge using exchange-traded foreign exchange derivatives. How...
What is the distinction between ethics and morality based on their scope?
According to the IRAC Norms, which of the following asset classifications applies to a loan where the borrower has defaulted on payment for over 12 mon...
In the preparation and presentation of financial statements, certain components are essential to provide a complete and transparent view of a company's ...
ABC Ltd stated the reason of poor performance of the company was the unsystematic risks faced by it in the current financial year. Which of the followin...
What is the name of the regulatory body that oversees the functioning of commodity futures trading in India?
Which global organization published the World Investment Report 2024?
Which of the following statements is correct regarding the RBI’s Master Direction on KYC for CPs and NCDs?
What is the purpose of the Udyam Assist Portal (UAP) certificate issued to Informal Micro Enterprises (IMEs)?
Sale of a security that is not owned by the seller is called?