📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store

    • Question

      Person A is 40% more efficient than person B, while person

      C is 40% less efficient than person B. All three—A, B, and C—can together finish a task in 35 days. If only A and B work on the task for the first 40 days, how many additional days will C alone need to complete the remaining work?
      A 12.5 days Correct Answer Incorrect Answer
      B 15 days Correct Answer Incorrect Answer
      C 17.5 days Correct Answer Incorrect Answer
      D 25 days Correct Answer Incorrect Answer

      Solution

      Let efficiency of ‘B’ is ‘x’ units per day
      Efficiency of ‘A’ = 1.40 × x = 1.4x units per day
      Efficiency of ‘C’ = 0.60 × x = 0.6x units per day
      Total work = (1.4x + x + 0.6x) × 35 = 105x units
      Amount of work done by ‘A’ and ‘B’ together in 40 days = 40 × (1.4x + x) = 96x units
      Desired time = (105x – 96x)/0.6x = 15 days

      Practice Next
      ask-question