      Question

      Which function allows the Board to modify or reject

      proposals for providing infrastructure facilities in a SEZ?
      A Power under Section 10 Correct Answer Incorrect Answer
      B Approval of authorized operations by the Developer Correct Answer Incorrect Answer
      C Power under Section 9(2)(d) Correct Answer Incorrect Answer
      D Approvals under the Companies Act Correct Answer Incorrect Answer
      E Issuance of licenses under municipal law Correct Answer Incorrect Answer

      Solution

      Explanation: Section 9(2)(d) explicitly states the Board’s power to grant, modify, or reject proposals concerning infrastructure facilities in SEZs.